Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
A. If such facility is proposed to be located in a village, the chief executive officer representing the town shall nominate four candidates, the chief executive officer representing the county shall nominate four candidates, and the chief executive officer representing the village shall nominate four candidates for consideration. The list of candidates is to be submitted to the President Pro Tem of the Senate or the Speaker of the Assembly within fifteen days of receipt of notification of the pre-application preliminary scoping statement.
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
A. Applicants must submit proposed Public Involvement Program plans in writing to the Department of Public Service for review as to their adequacy at least 150 days prior to the submittal of any preliminary scoping statement. For good cause, applicants may request a reduction in the minimum number of days to less than 150.
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
A. Applicants are required to identify significant non-English speaking populations and to address the need for non-English communication and participation in their Public Involvement Program plan.
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT



A. The information that must be included falls into two major categories. The first category is a description of the proposed facility and its environmental setting. Among other things, the information provided must include the description of potential environmental and health impacts resulting from the construction and operation of the proposed facility; measures proposed to minimize environmental impacts; reasonable alternatives to the facility; and the identification of all other state and federal permits, certifications, or other authorizations needed for construction, operation or maintenance of the proposed facility. The second category is a description of the proposed studies or program of studies designed to evaluate potential environmental and health impacts that the applicant intends to include in its application for an Article 10 certificate. The description of the studies must include the extent and quality of information needed for the application to adequately address and evaluate each potentially significant adverse environmental and health impact, including existing and new information where required, and the methodologies and procedures for obtaining the new information. The preliminary scoping statement must also include an identification of any other material issues raised by the public and affected agencies during any consultation and the response of the applicant to those issues.

PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





A. The presiding examiner will provide for an expedited pre-application funding disbursement schedule to assure early and meaningful public involvement. Following receipt of initial requests for pre-application funds, the presiding examiner shall expeditiously make an initial award of pre-application funds. Subject to the availability of funds, the presiding examiner may fix additional dates for submission of fund requests. Thereafter the presiding examiner may make additional awards of pre-application funds, in relation to the potential for such awards to make an effective contribution to review of the preliminary scoping statement.



PRE-APPLICATION PROCEDURES - STIPULATIONS



A. Yes. Before a stipulation may be executed, notice of the proposed stipulation must be provided and the public and other parties must be afforded a reasonable opportunity to submit comments on the proposed stipulation before it is executed by the interested parties.

APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



A. If the documents submitted are sufficient to comply with the requirements of the law, regulations and stipulations, the Chairperson of the Siting Board will issue a letter to the applicant advising that the documents submitted constitute a complying application. The Chairperson will also fix the date for the commencement of a public hearing and the Department of Environmental Conservation will initiate its review pursuant to federally delegated or approved environmental permitting authority or air and water permit applications. Within a reasonable time, the presiding examiner will hold a prehearing conference to expedite the orderly conduct and completion of the hearing, to specify the issues, to obtain stipulations as to matters not disputed, and to deal with other matters deemed appropriate. The presiding examiner will then issue an order identifying the issues to be addressed by the parties. Later in the proceeding there may also be a consideration of additional issues which warrant consideration in order to develop an adequate record.
APPLICATION PROCEDURES - DESIGNATION OF PARTIES


A. The applicant, staff of the Department of Public Service, the Department of Environmental Conservation, the Department of Economic Development, the Department of Health, the Department of Agriculture and Markets, the New York State Energy Research and Development Authority, the Department of State, the Office of Parks, Recreation and Historic Preservation, and in certain instances, the Adirondack Park Agency.


A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT
