Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
A. A "certificate" is a legal document issued by the Siting Board to an applicant if the Siting Board determines that the applicant's proposal to construct and operate a major electric generating facility satisfies the statutory standards set forth in Article 10 of the Public Service Law. The certificate authorizes the applicant to construct and operate the proposed facility. The certificate must be in the form of a written decision and opinion, must include explicit findings and determinations required by the statute, and must state the reasons of the Siting Board for the action taken.
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
A. Public involvement is intended to be a proactive process that begins during the planning of a preliminary scoping statement before it is filed, and continues throughout the planning, pre-application, certification, compliance, construction, and operation processes.
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
A. Applicants are required to identify significant non-English speaking populations and to address the need for non-English communication and participation in their Public Involvement Program plan.
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT


A. The preliminary scoping statement must be filed no less than 90 days before the date on which the applicant files its application for an Article 10 certificate. In addition, at least three days before the preliminary scoping statement is filed, the applicant must publish a public notice and summary of the preliminary scoping statement in local newspapers in the affected area and serve a copy of the notice and summary upon public officials and all persons who requested to receive such notices.

A. The information that must be included falls into two major categories. The first category is a description of the proposed facility and its environmental setting. Among other things, the information provided must include the description of potential environmental and health impacts resulting from the construction and operation of the proposed facility; measures proposed to minimize environmental impacts; reasonable alternatives to the facility; and the identification of all other state and federal permits, certifications, or other authorizations needed for construction, operation or maintenance of the proposed facility. The second category is a description of the proposed studies or program of studies designed to evaluate potential environmental and health impacts that the applicant intends to include in its application for an Article 10 certificate. The description of the studies must include the extent and quality of information needed for the application to adequately address and evaluate each potentially significant adverse environmental and health impact, including existing and new information where required, and the methodologies and procedures for obtaining the new information. The preliminary scoping statement must also include an identification of any other material issues raised by the public and affected agencies during any consultation and the response of the applicant to those issues.

PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.








PRE-APPLICATION PROCEDURES - STIPULATIONS

A. "Stipulations" are agreements among parties that concern matters before the Siting Board and are designed to simplify or shorten litigation and save costs. Any parties to the proceeding can enter into a stipulation setting forth an agreement on any aspect of the preliminary scoping statement and the scope of studies or program of studies to be conducted. It is often in the interests of applicants and other parties to agree in advance to the content and methodology for conducting studies that will be submitted as part of the application.



APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES




A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING

A. The hearings will be conducted by a presiding examiner designated by the Department of Public Service. An associate examiner shall be designated by the Department of Environmental Conservation. The associate examiner will assist the presiding examiner in inquiring into and calling for testimony concerning relevant and material matters, and the conclusions and recommendations of the associate examiner will be incorporated in the recommended decision of the presiding examiner.






SITING BOARD DECISIONS - TIMING OF THE DECISION



A. Yes, but only in an unusual circumstance. If the proceeding is on certain qualifying applications by an owner of an existing major electric generating facility to modify that facility or site a new major electric generating facility adjacent or contiguous to the existing facility, the deadlines are different such that the final decision by the Siting Board must be completed within 6 months, the extension permitted in extraordinary circumstances is 3 months, and the extension permitted to consider a material and substantial amendment to the application is 3 months, unless the deadlines are waived by the applicant.
SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT