Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
A. A "facility" includes all the components of a power plant located on the site and may also include new interconnecting electric power lines and natural gas fuel pipelines. For example, a natural gas-fired facility would include a natural gas pipeline to bring fuel to the facility; a boiler to create steam; a turbine to be rotated by the steam; an electric generator to be turned by the turbine; a cooling system; exhaust stacks; various buildings to house the components; employee areas; back-up fuel storage tanks; ancillary equipment, parking and storage areas; an electric substation including transformers; and a transmission line to carry the electricity out to the grid. A wind-power facility would include wind turbines on towers with integrated electric generators; electric collection lines; access roads; an electric switchyard and substation including transformers; meteorological towers; and a transmission line to carry the electricity out to the grid.
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
A. The Siting Board is a governmental entity of New York State organized within the New York State Department of Public Service. The Siting Board was established primarily to review applications and to issue or deny certificates authorizing the construction and operation of major electric generating facilities. When the Siting Board is reviewing an original application for a certificate, it consists of five permanent members and two ad hoc public members. The five permanent members of the Siting Board also have additional responsibilities to promulgate regulations for the implementation of Article 10, and they have jurisdiction with respect to the amendment, suspension or revocation of a certificate.
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
A. Yes. The ad hoc appointees shall receive the sum of two hundred dollars for each day in which they are actually engaged in the performance of their duties plus actual and necessary expenses incurred by them in the performance of such duties.
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
A. Public involvement is intended to be a proactive process that begins during the planning of a preliminary scoping statement before it is filed, and continues throughout the planning, pre-application, certification, compliance, construction, and operation processes.
Q. How is public involvement conducted?
A. At the earliest stage of the Article 10 process, applicants are required to prepare and begin implementing a Public Involvement Program. In addition, to ensure that the public and interested parties are fully assisted and advised in participating in the Article 10 process, an Office of Public Information Coordinator has been created within the New York State Department of Public Service.
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT




PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.








PRE-APPLICATION PROCEDURES - STIPULATIONS




APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES




A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING



A. Public statement hearings are designed to obtain input from the general public. The format is designed for the taking of unsworn oral statements, although written statements ordinarily may also be submitted. Parties to the proceeding are not permitted to cross examine the persons making such statements.




SITING BOARD DECISIONS - TIMING OF THE DECISION


A. If during the proceeding there is a material and substantial amendment to the application, the deadlines may be extended by no more than 6 months to consider such amendment, unless the deadline is waived by the applicant.

SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT