Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
A. Applicants are required to identify significant non-English speaking populations and to address the need for non-English communication and participation in their Public Involvement Program plan.
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT


A. The preliminary scoping statement must be filed no less than 90 days before the date on which the applicant files its application for an Article 10 certificate. In addition, at least three days before the preliminary scoping statement is filed, the applicant must publish a public notice and summary of the preliminary scoping statement in local newspapers in the affected area and serve a copy of the notice and summary upon public officials and all persons who requested to receive such notices.


A. Within 21 days after the filing of the preliminary scoping statement, any person, agency or municipality may submit comments on the preliminary scoping statement by serving such comments on the applicant and filing a copy with the secretary. Within 21 days after the closing of the comment period, the applicant shall prepare a summary of the material comments and its reply thereto, and file and serve its summary of comments and its reply in the same manner as it files and serves the preliminary scoping statement. Thereafter, it is expected that the applicant will work with interested parties to resolve any disagreements they may have about the sufficiency of the planned scope and methodology of studies to be included in the application.
PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.








PRE-APPLICATION PROCEDURES - STIPULATIONS



A. Yes. Before a stipulation may be executed, notice of the proposed stipulation must be provided and the public and other parties must be afforded a reasonable opportunity to submit comments on the proposed stipulation before it is executed by the interested parties.

APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION


A. If the documents submitted are insufficient to comply with the requirements of the law, regulations and stipulations, the Chairperson of the Siting Board will issue a letter to the applicant advising of the deficiencies that must be corrected before the documents can be deemed a complying application. The Chairperson of the Siting Board may also require the filing of any additional information needed to supplement an application before or during the hearings.

APPLICATION PROCEDURES - DESIGNATION OF PARTIES





APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.

A. If the application amendment is deemed a revision requiring substantial additional scrutiny, the applicant will be assessed an additional intervenor fee equal to $1,000 for each 1,000 kilowatts of capacity of the proposed project, as amended, but no more than $75,000.00. The presiding examiner may increase the level of the additional intervenor fee up to the maximum level of $75,000 if the presiding examiner finds circumstances require a higher level of intervenor funding in order to ensure an adequate record.




HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





A. The Siting Board must consider: (a) the state of available technology; (b) the nature and economics of reasonable alternatives; (c) environmental impacts found pursuant to subdivision two of this section; (d) the impact of construction and operation of related facilities, such as electric lines, gas lines, water supply lines, waste water or other sewage treatment facilities, communications and relay facilities, access roads, rail facilities, or steam lines; (e) the consistency of the construction and operation of the facility with the energy policies and long-range energy planning objectives and strategies contained in the most recent state energy plan; (f) the impact on community character and whether the facility would affect communities that are disproportionately impacted by cumulative levels of pollutants; and (g) such additional social, economic, visual or other aesthetic, environmental and other considerations deemed pertinent by the Siting Board.
COMPLIANCE AND ENFORCEMENT
