Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
A. In such a situation, parties would be free to seek procedural and substantive remedies in the Article 10 process.
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT

A. A preliminary scoping statement is a written document to inform the Siting Board, other public agencies and the public that the applicant is contemplating making an Article 10 application. It is prepared by an applicant after consulting with the public, affected agencies, and other stakeholders. The term "consulting" in this context means providing information to and effective opportunities for input from the public, affected agencies, and other stakeholders, concerning the proposal.


A. The information that must be included falls into two major categories. The first category is a description of the proposed facility and its environmental setting. Among other things, the information provided must include the description of potential environmental and health impacts resulting from the construction and operation of the proposed facility; measures proposed to minimize environmental impacts; reasonable alternatives to the facility; and the identification of all other state and federal permits, certifications, or other authorizations needed for construction, operation or maintenance of the proposed facility. The second category is a description of the proposed studies or program of studies designed to evaluate potential environmental and health impacts that the applicant intends to include in its application for an Article 10 certificate. The description of the studies must include the extent and quality of information needed for the application to adequately address and evaluate each potentially significant adverse environmental and health impact, including existing and new information where required, and the methodologies and procedures for obtaining the new information. The preliminary scoping statement must also include an identification of any other material issues raised by the public and affected agencies during any consultation and the response of the applicant to those issues.

PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.








PRE-APPLICATION PROCEDURES - STIPULATIONS



A. Yes. Before a stipulation may be executed, notice of the proposed stipulation must be provided and the public and other parties must be afforded a reasonable opportunity to submit comments on the proposed stipulation before it is executed by the interested parties.

APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES




A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION



A. The Siting Board must make explicit findings regarding the nature of the probable environmental impacts of the construction and operation of the facility, including the cumulative environmental impacts of the construction and operation of related facilities such as electric lines, gas lines, water supply lines, waste water or other sewage treatment facilities, communications and relay facilities, access roads, rail facilities, or steam lines, including impacts on: (a) ecology, air, ground and surface water, wildlife, and habitat;
(b) public health and safety; (c) cultural, historic, and recreational resources, including aesthetics and scenic values; and (d) transportation, communication, utilities and other infrastructure. Such findings shall include the cumulative impact of emissions on the local community including whether the construction and operation of the facility results in a significant and adverse disproportionate environmental impact, in accordance with regulations promulgated by the Department of Environmental Conservation regarding environmental justice issues.


COMPLIANCE AND ENFORCEMENT
