BASIC CONCEPTS
Q. What is Article 10?
A. "Article 10" was enacted in 2011 to be a portion of the New York State Public Service Law. It is a general state law that is applicable in all of New York State. Article 10 empowers the New York State Board on Electric Generation Siting and the Environment (Siting Board) to issue Certificates of Environmental Compatibility and Public Need (certificate) authorizing the construction and operation of major electric generating facilities.
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
A. Yes. The statute provides exemption for:
(a) electric generating facilities with a generating capacity of less than 25 megawatts;
(b) electric generating facilities for which the federal government has exclusive siting jurisdiction;
(c) electric generating facilities for which the federal government has concurrent siting jurisdiction and has exercised such jurisdiction to the exclusion of state regulation;
(d) normal repairs, replacements, modifications and improvements of a major electric generating facility, whenever built, which do not constitute a violation of any Article 10 certificate and which do not result in an increase in capacity of the facility of more than 25 megawatts;
(e) electric generating facilities of 200 megawatts or less constructed on lands dedicated to industrial uses where the electricity generated is used solely for industrial purposes on the premises;
(f) electric generating facilities for which an application was made on or before July 12, 2012 for a license, permit, certificate, consent or approval from any federal, state or local commission, agency, board or regulatory body; and.
(g) electric generating facilities under construction on July 12, 2012.
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
A. "Public involvement" is the process of enabling the public to participate in decisions that may affect public health, safety and the environment.
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
A. The Office of Public Information Coordinator assists the public and interested parties by: (a) implementing measures that assure public participation in matters before the Siting Board; (b) responding to inquiries from the public for information on how to participate; (c) assisting the public in requesting records; (d) ensuring all interested persons are provided with a reasonable opportunity to participate at public meetings; (e) ensuring that all necessary or required documents are available for public access on the Siting Board website; and (f) any other duties as may be prescribed by the Siting Board, after consultation with the Department of Public Service.
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT




A. Within 21 days after the filing of the preliminary scoping statement, any person, agency or municipality may submit comments on the preliminary scoping statement by serving such comments on the applicant and filing a copy with the secretary. Within 21 days after the closing of the comment period, the applicant shall prepare a summary of the material comments and its reply thereto, and file and serve its summary of comments and its reply in the same manner as it files and serves the preliminary scoping statement. Thereafter, it is expected that the applicant will work with interested parties to resolve any disagreements they may have about the sufficiency of the planned scope and methodology of studies to be included in the application.
PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





A. The presiding examiner will provide for an expedited pre-application funding disbursement schedule to assure early and meaningful public involvement. Following receipt of initial requests for pre-application funds, the presiding examiner shall expeditiously make an initial award of pre-application funds. Subject to the availability of funds, the presiding examiner may fix additional dates for submission of fund requests. Thereafter the presiding examiner may make additional awards of pre-application funds, in relation to the potential for such awards to make an effective contribution to review of the preliminary scoping statement.



PRE-APPLICATION PROCEDURES - STIPULATIONS




APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES




A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.

A. If the application amendment is deemed a revision requiring substantial additional scrutiny, the applicant will be assessed an additional intervenor fee equal to $1,000 for each 1,000 kilowatts of capacity of the proposed project, as amended, but no more than $75,000.00. The presiding examiner may increase the level of the additional intervenor fee up to the maximum level of $75,000 if the presiding examiner finds circumstances require a higher level of intervenor funding in order to ensure an adequate record.



A. The intervenor funds awarded can be used to defray expenses incurred by municipal and local parties for expert witnesses, consultants, administrative costs (document preparation and duplications costs) and legal fees. No intervenor funds may be used to pay for judicial review or litigation costs.

HEARING PROCEDURES - CONDUCT OF THE HEARING


A. It is expected that both public statement hearings and trial-type evidentiary hearings will be held. In addition, persons are permitted to make a limited appearance.





SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT