Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
A. To be eligible to be an ad hoc public member, the person must:
(a) be eighteen years of age or older,
(b) be a citizen of the United States;
(c) be a resident of New York State;
(d) be a resident of the municipality in which the facility is proposed to be located (if such facility is proposed to be located within the City of New York, the person must also be a resident of the community district in which the facility is proposed to be located);
(e) not hold another state or local office; and
(f) not retain or hold any official relation to, or any securities of an electric utility corporation operating in the state or proposed for operation in the state, any affiliate thereof or any other company, firm, partnership, corporation, association or joint-stock association that may appear before the Siting Board, nor shall the person have been a director, officer or, within the previous ten years, an employee thereof.
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
A. "Public involvement" is the process of enabling the public to participate in decisions that may affect public health, safety and the environment.
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
A. Applicants are required to identify significant non-English speaking populations and to address the need for non-English communication and participation in their Public Involvement Program plan.
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT



A. The information that must be included falls into two major categories. The first category is a description of the proposed facility and its environmental setting. Among other things, the information provided must include the description of potential environmental and health impacts resulting from the construction and operation of the proposed facility; measures proposed to minimize environmental impacts; reasonable alternatives to the facility; and the identification of all other state and federal permits, certifications, or other authorizations needed for construction, operation or maintenance of the proposed facility. The second category is a description of the proposed studies or program of studies designed to evaluate potential environmental and health impacts that the applicant intends to include in its application for an Article 10 certificate. The description of the studies must include the extent and quality of information needed for the application to adequately address and evaluate each potentially significant adverse environmental and health impact, including existing and new information where required, and the methodologies and procedures for obtaining the new information. The preliminary scoping statement must also include an identification of any other material issues raised by the public and affected agencies during any consultation and the response of the applicant to those issues.

A. Within 21 days after the filing of the preliminary scoping statement, any person, agency or municipality may submit comments on the preliminary scoping statement by serving such comments on the applicant and filing a copy with the secretary. Within 21 days after the closing of the comment period, the applicant shall prepare a summary of the material comments and its reply thereto, and file and serve its summary of comments and its reply in the same manner as it files and serves the preliminary scoping statement. Thereafter, it is expected that the applicant will work with interested parties to resolve any disagreements they may have about the sufficiency of the planned scope and methodology of studies to be included in the application.
PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.




A. If the pre-application preliminary scoping statement is substantially modified or revised, the Siting Board may require an additional pre-application intervenor fee in an amount not to exceed $25,000.


A. The presiding examiner will provide for an expedited pre-application funding disbursement schedule to assure early and meaningful public involvement. Following receipt of initial requests for pre-application funds, the presiding examiner shall expeditiously make an initial award of pre-application funds. Subject to the availability of funds, the presiding examiner may fix additional dates for submission of fund requests. Thereafter the presiding examiner may make additional awards of pre-application funds, in relation to the potential for such awards to make an effective contribution to review of the preliminary scoping statement.


A. The pre-application intervenor funds awarded can be used to defray pre-application expenses incurred by municipal and local parties for expert witnesses, consultants, administrative costs (document preparation and duplications costs) and legal fees. No intervenor funds may be used to pay for judicial review or litigation costs.

PRE-APPLICATION PROCEDURES - STIPULATIONS


A. So that all parties will have an opportunity to participate, the applicant may not commence consultations or seek agreements on proposed stipulations until the pre-application intervenor funds have been allocated by the presiding examiner. Within sixty days of the filing of a preliminary scoping statement, the presiding examiner will convene a meeting of interested parties in order to initiate the stipulation process. The presiding examiner will also oversee the pre-application process and mediate any issue relating to any aspect of the preliminary scoping statement and the methodology and scope of any such studies or programs of study in order to attempt to resolve any questions that may arise.


APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES




A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT
