Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
A. A "facility" includes all the components of a power plant located on the site and may also include new interconnecting electric power lines and natural gas fuel pipelines. For example, a natural gas-fired facility would include a natural gas pipeline to bring fuel to the facility; a boiler to create steam; a turbine to be rotated by the steam; an electric generator to be turned by the turbine; a cooling system; exhaust stacks; various buildings to house the components; employee areas; back-up fuel storage tanks; ancillary equipment, parking and storage areas; an electric substation including transformers; and a transmission line to carry the electricity out to the grid. A wind-power facility would include wind turbines on towers with integrated electric generators; electric collection lines; access roads; an electric switchyard and substation including transformers; meteorological towers; and a transmission line to carry the electricity out to the grid.
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
A. Based on recent market trends in New York State, the types of electric generating facilities most likely to be proposed pursuant to the Article 10 process are natural gas-fired facilities and wind-power facilities. But it is possible that other types of generating facilities will be proposed. The Summer 2012 installed generating capacity of power plants in the New York Control Area is 38,902 MWs, type classified as follows: Gas with Oil Back-up 36.9%; Gas 15.7%; Nuclear 13.5%; Hydro 11.0%; Oil 8.5%; Coal 6.1%; Pumped Storage Hydro 3.6%, Wind 3.5%; Refuse 0.7%; Biomass (Wood) 0.1%; Solar 0.1%, and Other 0.2%.
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
A. No. There are three power authorities in New York State: the Power Authority of the State of New York (NYPA); the Green Island Power Authority; and the Long Island Power Authority (LIPA). The statute expressly provides that all three authorities are subject to the provisions of the Article 10 siting process for major electric generating facilities which they build or cause to be built.
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT

A. A preliminary scoping statement is a written document to inform the Siting Board, other public agencies and the public that the applicant is contemplating making an Article 10 application. It is prepared by an applicant after consulting with the public, affected agencies, and other stakeholders. The term "consulting" in this context means providing information to and effective opportunities for input from the public, affected agencies, and other stakeholders, concerning the proposal.

A. The preliminary scoping statement must be filed no less than 90 days before the date on which the applicant files its application for an Article 10 certificate. In addition, at least three days before the preliminary scoping statement is filed, the applicant must publish a public notice and summary of the preliminary scoping statement in local newspapers in the affected area and serve a copy of the notice and summary upon public officials and all persons who requested to receive such notices.


PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.








PRE-APPLICATION PROCEDURES - STIPULATIONS




APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES




A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING

A. The hearings will be conducted by a presiding examiner designated by the Department of Public Service. An associate examiner shall be designated by the Department of Environmental Conservation. The associate examiner will assist the presiding examiner in inquiring into and calling for testimony concerning relevant and material matters, and the conclusions and recommendations of the associate examiner will be incorporated in the recommended decision of the presiding examiner.






A. A written transcript record is made of the hearings and of all testimony taken and the cross-examinations thereon. In addition, the presiding examiner will provide a summary of the proceedings in a recommended decision that will be presented to the Siting Board. The parties will also present legal briefs to the Siting Board with citations to the portions of the record they deem relevant to their positions.
SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION

A. The Siting Board can grant a certificate in the manner requested by the applicant, it can grant a certificate subject to modifications and or conditions, or it may deny the application. In rendering a decision on an application for a certificate, the Siting Board must issue a written opinion stating its reasons for the action taken.




COMPLIANCE AND ENFORCEMENT