BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
A. A "facility" includes all the components of a power plant located on the site and may also include new interconnecting electric power lines and natural gas fuel pipelines. For example, a natural gas-fired facility would include a natural gas pipeline to bring fuel to the facility; a boiler to create steam; a turbine to be rotated by the steam; an electric generator to be turned by the turbine; a cooling system; exhaust stacks; various buildings to house the components; employee areas; back-up fuel storage tanks; ancillary equipment, parking and storage areas; an electric substation including transformers; and a transmission line to carry the electricity out to the grid. A wind-power facility would include wind turbines on towers with integrated electric generators; electric collection lines; access roads; an electric switchyard and substation including transformers; meteorological towers; and a transmission line to carry the electricity out to the grid.
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
A. Yes. The ad hoc appointees shall receive the sum of two hundred dollars for each day in which they are actually engaged in the performance of their duties plus actual and necessary expenses incurred by them in the performance of such duties.
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
A. The New York State Department of Public Service is one of 20 major departments in New York State government. The Siting Board is a decision-making body organized within the Department of Public Service. The Public Service Commission is another decision-making body organized within the Department of Public Service. The Chairman of the Public Service Commission also serves as chief executive of the Department of Public Service and Chairperson of the Siting Board. The staff of the Department of Public Service represent the public interest in all Siting Board proceedings, under the direction of the Chairperson.
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT




PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.



A. If the pre-application preliminary scoping statement is substantially modified or revised, the Siting Board may require an additional pre-application intervenor fee in an amount not to exceed $25,000.





PRE-APPLICATION PROCEDURES - STIPULATIONS




A. No party that is not a signatory to the stipulation is barred from timely raising objections to any aspect of the preliminary scoping statement and the methodology and scope of any stipulated studies or program of studies in any such stipulation. A party that is a signatory to the stipulation may not object to any aspect of the preliminary scoping statement and the methodology and scope of any stipulated studies or program of studies covered in any such stipulation, unless the applicant fails to comply with the stipulation.
APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES


A. The applicant, staff of the Department of Public Service, the Department of Environmental Conservation, the Department of Economic Development, the Department of Health, the Department of Agriculture and Markets, the New York State Energy Research and Development Authority, the Department of State, the Office of Parks, Recreation and Historic Preservation, and in certain instances, the Adirondack Park Agency.


A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT