BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
A. A "facility" includes all the components of a power plant located on the site and may also include new interconnecting electric power lines and natural gas fuel pipelines. For example, a natural gas-fired facility would include a natural gas pipeline to bring fuel to the facility; a boiler to create steam; a turbine to be rotated by the steam; an electric generator to be turned by the turbine; a cooling system; exhaust stacks; various buildings to house the components; employee areas; back-up fuel storage tanks; ancillary equipment, parking and storage areas; an electric substation including transformers; and a transmission line to carry the electricity out to the grid. A wind-power facility would include wind turbines on towers with integrated electric generators; electric collection lines; access roads; an electric switchyard and substation including transformers; meteorological towers; and a transmission line to carry the electricity out to the grid.
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
A. "Ad hoc" is a Latin term meaning "for this special purpose". Two ad hoc members will be appointed for the special purpose of providing a local voice in each proceeding conducted to consider specific individual applications for certificates. Each facility application will have its own associated ad hoc members.
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
A. No. There are three power authorities in New York State: the Power Authority of the State of New York (NYPA); the Green Island Power Authority; and the Long Island Power Authority (LIPA). The statute expressly provides that all three authorities are subject to the provisions of the Article 10 siting process for major electric generating facilities which they build or cause to be built.
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
A. At the earliest stage of the Article 10 process, applicants are required to prepare and begin implementing a Public Involvement Program. In addition, to ensure that the public and interested parties are fully assisted and advised in participating in the Article 10 process, an Office of Public Information Coordinator has been created within the New York State Department of Public Service.
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
A. Applicants must submit proposed Public Involvement Program plans in writing to the Department of Public Service for review as to their adequacy at least 150 days prior to the submittal of any preliminary scoping statement. For good cause, applicants may request a reduction in the minimum number of days to less than 150.
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT




PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.



A. If the pre-application preliminary scoping statement is substantially modified or revised, the Siting Board may require an additional pre-application intervenor fee in an amount not to exceed $25,000.





PRE-APPLICATION PROCEDURES - STIPULATIONS




APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES



A. Provided they file with the Siting Board a notice of intent to be a party, within 45 days after the date given in the published notice as the date for the filing of the application, the following parties have a right to be a party to an Article 10 proceeding merely by giving the required notice: (a) the affected municipality; (b) any individual resident of an affected municipality; (c) any non-profit corporation or association, formed in whole or in part to promote conservation or natural beauty, to protect the environment, personal health or other biological values, to preserve historical sites, to promote consumer interests, to represent commercial and industrial groups or to promote the orderly development of any area in which the facility is to be located; and (d) any other municipality or resident of such municipality located within a five mile radius of such proposed facility (their notice of intent must include an explanation of the potential environmental effects on such municipality or person). In addition, the presiding officer may for good cause shown permit a municipality or other person to become a party and to participate in all subsequent stages of the proceeding.

A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.

A. If the application amendment is deemed a revision requiring substantial additional scrutiny, the applicant will be assessed an additional intervenor fee equal to $1,000 for each 1,000 kilowatts of capacity of the proposed project, as amended, but no more than $75,000.00. The presiding examiner may increase the level of the additional intervenor fee up to the maximum level of $75,000 if the presiding examiner finds circumstances require a higher level of intervenor funding in order to ensure an adequate record.




HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT