BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
A. A "certificate" is a legal document issued by the Siting Board to an applicant if the Siting Board determines that the applicant's proposal to construct and operate a major electric generating facility satisfies the statutory standards set forth in Article 10 of the Public Service Law. The certificate authorizes the applicant to construct and operate the proposed facility. The certificate must be in the form of a written decision and opinion, must include explicit findings and determinations required by the statute, and must state the reasons of the Siting Board for the action taken.
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
A. The five permanent members of the Siting Board are the Chairman of the Department of Public Service who serves as chairperson of the Siting Board; the Commissioner of the Department of Environmental Conservation; the Commissioner of the Department of Health; the Chairperson of the New York State Energy Research and Development Authority; and the Commissioner of Economic Development. The permanent members may designate an alternate to serve instead of the member with respect to all proceedings provided that such designation is in writing and filed with the chairperson.
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
A. Applicants are required to identify significant non-English speaking populations and to address the need for non-English communication and participation in their Public Involvement Program plan.
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT


A. The preliminary scoping statement must be filed no less than 90 days before the date on which the applicant files its application for an Article 10 certificate. In addition, at least three days before the preliminary scoping statement is filed, the applicant must publish a public notice and summary of the preliminary scoping statement in local newspapers in the affected area and serve a copy of the notice and summary upon public officials and all persons who requested to receive such notices.


A. Within 21 days after the filing of the preliminary scoping statement, any person, agency or municipality may submit comments on the preliminary scoping statement by serving such comments on the applicant and filing a copy with the secretary. Within 21 days after the closing of the comment period, the applicant shall prepare a summary of the material comments and its reply thereto, and file and serve its summary of comments and its reply in the same manner as it files and serves the preliminary scoping statement. Thereafter, it is expected that the applicant will work with interested parties to resolve any disagreements they may have about the sufficiency of the planned scope and methodology of studies to be included in the application.
PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.








PRE-APPLICATION PROCEDURES - STIPULATIONS


A. So that all parties will have an opportunity to participate, the applicant may not commence consultations or seek agreements on proposed stipulations until the pre-application intervenor funds have been allocated by the presiding examiner. Within sixty days of the filing of a preliminary scoping statement, the presiding examiner will convene a meeting of interested parties in order to initiate the stipulation process. The presiding examiner will also oversee the pre-application process and mediate any issue relating to any aspect of the preliminary scoping statement and the methodology and scope of any such studies or programs of study in order to attempt to resolve any questions that may arise.


APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES



A. Provided they file with the Siting Board a notice of intent to be a party, within 45 days after the date given in the published notice as the date for the filing of the application, the following parties have a right to be a party to an Article 10 proceeding merely by giving the required notice: (a) the affected municipality; (b) any individual resident of an affected municipality; (c) any non-profit corporation or association, formed in whole or in part to promote conservation or natural beauty, to protect the environment, personal health or other biological values, to preserve historical sites, to promote consumer interests, to represent commercial and industrial groups or to promote the orderly development of any area in which the facility is to be located; and (d) any other municipality or resident of such municipality located within a five mile radius of such proposed facility (their notice of intent must include an explanation of the potential environmental effects on such municipality or person). In addition, the presiding officer may for good cause shown permit a municipality or other person to become a party and to participate in all subsequent stages of the proceeding.

A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING



A. Public statement hearings are designed to obtain input from the general public. The format is designed for the taking of unsworn oral statements, although written statements ordinarily may also be submitted. Parties to the proceeding are not permitted to cross examine the persons making such statements.




SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT