Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
A. The Department of Public Service provides a presiding examiner and whatever legal, technological, scientific, engineering and other services that may be required. The Department of Environmental Conservation provides an associate examiner. The Secretary and the General Counsel to the Public Service Commission serve as Secretary and the General Counsel to the Siting Board.
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
A. "Public involvement" is the process of enabling the public to participate in decisions that may affect public health, safety and the environment.
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
A. Applicants must submit proposed Public Involvement Program plans in writing to the Department of Public Service for review as to their adequacy at least 150 days prior to the submittal of any preliminary scoping statement. For good cause, applicants may request a reduction in the minimum number of days to less than 150.
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT

A. A preliminary scoping statement is a written document to inform the Siting Board, other public agencies and the public that the applicant is contemplating making an Article 10 application. It is prepared by an applicant after consulting with the public, affected agencies, and other stakeholders. The term "consulting" in this context means providing information to and effective opportunities for input from the public, affected agencies, and other stakeholders, concerning the proposal.



PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.



A. Applicants submitting a preliminary scoping statement are assessed an intervenor fee equal to $350 for each 1,000 kilowatts (1 megawatt) of generating capacity of the subject facility, but no more than $200,000. For example, for a 100 megawatt facility, the pre-application intervenor fee would be $35,000 (100 x $350).



A. The presiding examiner will provide for an expedited pre-application funding disbursement schedule to assure early and meaningful public involvement. Following receipt of initial requests for pre-application funds, the presiding examiner shall expeditiously make an initial award of pre-application funds. Subject to the availability of funds, the presiding examiner may fix additional dates for submission of fund requests. Thereafter the presiding examiner may make additional awards of pre-application funds, in relation to the potential for such awards to make an effective contribution to review of the preliminary scoping statement.



PRE-APPLICATION PROCEDURES - STIPULATIONS




APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES





APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



A. Yes, but only in an unusual circumstance. If the proceeding is on certain qualifying applications by an owner of an existing major electric generating facility to modify that facility or site a new major electric generating facility adjacent or contiguous to the existing facility, the deadlines are different such that the final decision by the Siting Board must be completed within 6 months, the extension permitted in extraordinary circumstances is 3 months, and the extension permitted to consider a material and substantial amendment to the application is 3 months, unless the deadlines are waived by the applicant.
SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT
