Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
A. An electric generating facility is deemed to be "major" if it has the capacity to generate 25,000 kilowatts (25 megawatts) or more of electricity. The 25 megawatt threshold is roughly equivalent to the average electric power needs of 30,000 households in New York State.
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
A. Applicants are required to identify significant non-English speaking populations and to address the need for non-English communication and participation in their Public Involvement Program plan.
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT




PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.



A. If the pre-application preliminary scoping statement is substantially modified or revised, the Siting Board may require an additional pre-application intervenor fee in an amount not to exceed $25,000.


A. The presiding examiner will provide for an expedited pre-application funding disbursement schedule to assure early and meaningful public involvement. Following receipt of initial requests for pre-application funds, the presiding examiner shall expeditiously make an initial award of pre-application funds. Subject to the availability of funds, the presiding examiner may fix additional dates for submission of fund requests. Thereafter the presiding examiner may make additional awards of pre-application funds, in relation to the potential for such awards to make an effective contribution to review of the preliminary scoping statement.



PRE-APPLICATION PROCEDURES - STIPULATIONS




APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES



A. Provided they file with the Siting Board a notice of intent to be a party, within 45 days after the date given in the published notice as the date for the filing of the application, the following parties have a right to be a party to an Article 10 proceeding merely by giving the required notice: (a) the affected municipality; (b) any individual resident of an affected municipality; (c) any non-profit corporation or association, formed in whole or in part to promote conservation or natural beauty, to protect the environment, personal health or other biological values, to preserve historical sites, to promote consumer interests, to represent commercial and industrial groups or to promote the orderly development of any area in which the facility is to be located; and (d) any other municipality or resident of such municipality located within a five mile radius of such proposed facility (their notice of intent must include an explanation of the potential environmental effects on such municipality or person). In addition, the presiding officer may for good cause shown permit a municipality or other person to become a party and to participate in all subsequent stages of the proceeding.

A. Such other persons or entities as the Siting Board may at any time deem appropriate, who may participate in all subsequent stages of the proceeding.

APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





A. The presiding examiner will award funds on an equitable basis to municipal and local parties who will use them to contribute to a complete record leading to an informed decision as to the appropriateness of the site and the facility and will facilitate broad participation in the proceeding.
HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION




A. The Siting Board must make explicit determinations that: (a) the facility is a beneficial addition to or substitution for the electric generation capacity of the state; (b) the construction and operation of the facility will serve the public interest; (c) the adverse environmental effects of the construction and operation of the facility will be minimized or avoided to the maximum extent practicable; (d) if the board finds that the facility results in or contributes to a significant and adverse disproportionate environmental impact in the community in which the facility would be located, the applicant will avoid, offset or minimize the impacts caused by the facility upon the local community for the duration that the certificate is issued to the maximum extent practicable using verifiable measures; (e) the facility is designed to operate in compliance with applicable state and local laws and regulations issued thereunder concerning, among other matters, the environment, public health and safety, all of which shall be binding upon the applicant, except that the Siting Board may elect not to apply, in whole or in part, any local ordinance, law, resolution or other action or any regulation issued thereunder or any local standard or requirement, including, but not limited to, those relating to the interconnection to and use of water, electric, sewer, telecommunication, fuel and steam lines in public rights of way, which would be otherwise applicable if it finds that, as applied to the proposed facility, such is unreasonably burdensome in view of the existing technology or the needs of or costs to ratepayers whether located inside or outside of such municipality. The Siting Board shall provide the municipality an opportunity to present evidence in support of such ordinance, law, resolution, regulation or other local action issued thereunder.

A. The Siting Board must consider: (a) the state of available technology; (b) the nature and economics of reasonable alternatives; (c) environmental impacts found pursuant to subdivision two of this section; (d) the impact of construction and operation of related facilities, such as electric lines, gas lines, water supply lines, waste water or other sewage treatment facilities, communications and relay facilities, access roads, rail facilities, or steam lines; (e) the consistency of the construction and operation of the facility with the energy policies and long-range energy planning objectives and strategies contained in the most recent state energy plan; (f) the impact on community character and whether the facility would affect communities that are disproportionately impacted by cumulative levels of pollutants; and (g) such additional social, economic, visual or other aesthetic, environmental and other considerations deemed pertinent by the Siting Board.
COMPLIANCE AND ENFORCEMENT
