Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
A. A "certificate" is a legal document issued by the Siting Board to an applicant if the Siting Board determines that the applicant's proposal to construct and operate a major electric generating facility satisfies the statutory standards set forth in Article 10 of the Public Service Law. The certificate authorizes the applicant to construct and operate the proposed facility. The certificate must be in the form of a written decision and opinion, must include explicit findings and determinations required by the statute, and must state the reasons of the Siting Board for the action taken.
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
A. "Ad hoc" is a Latin term meaning "for this special purpose". Two ad hoc members will be appointed for the special purpose of providing a local voice in each proceeding conducted to consider specific individual applications for certificates. Each facility application will have its own associated ad hoc members.
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
A. There is a different procedure depending on whether the facility is proposed to be located (a) in the City of New York; (b) in a town outside of any villages or in a city other than the City of New York; or (c) in a village.
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
A. If such facility is proposed to be located in a village, the chief executive officer representing the town shall nominate four candidates, the chief executive officer representing the county shall nominate four candidates, and the chief executive officer representing the village shall nominate four candidates for consideration. The list of candidates is to be submitted to the President Pro Tem of the Senate or the Speaker of the Assembly within fifteen days of receipt of notification of the pre-application preliminary scoping statement.
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
A. In such a situation, parties would be free to seek procedural and substantive remedies in the Article 10 process.
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT




PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.








PRE-APPLICATION PROCEDURES - STIPULATIONS




APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES

A. There are three kinds of parties: (a) automatic statutory parties; (b) parties that have a right to be a party merely by giving notice; and (c) parties that may be permitted to join.




APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





HEARING PROCEDURES - CONDUCT OF THE HEARING

A. The hearings will be conducted by a presiding examiner designated by the Department of Public Service. An associate examiner shall be designated by the Department of Environmental Conservation. The associate examiner will assist the presiding examiner in inquiring into and calling for testimony concerning relevant and material matters, and the conclusions and recommendations of the associate examiner will be incorporated in the recommended decision of the presiding examiner.






A. A written transcript record is made of the hearings and of all testimony taken and the cross-examinations thereon. In addition, the presiding examiner will provide a summary of the proceedings in a recommended decision that will be presented to the Siting Board. The parties will also present legal briefs to the Siting Board with citations to the portions of the record they deem relevant to their positions.
SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION



A. The Siting Board must make explicit findings regarding the nature of the probable environmental impacts of the construction and operation of the facility, including the cumulative environmental impacts of the construction and operation of related facilities such as electric lines, gas lines, water supply lines, waste water or other sewage treatment facilities, communications and relay facilities, access roads, rail facilities, or steam lines, including impacts on: (a) ecology, air, ground and surface water, wildlife, and habitat;
(b) public health and safety; (c) cultural, historic, and recreational resources, including aesthetics and scenic values; and (d) transportation, communication, utilities and other infrastructure. Such findings shall include the cumulative impact of emissions on the local community including whether the construction and operation of the facility results in a significant and adverse disproportionate environmental impact, in accordance with regulations promulgated by the Department of Environmental Conservation regarding environmental justice issues.


COMPLIANCE AND ENFORCEMENT