Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
A. The Siting Board is a governmental entity of New York State organized within the New York State Department of Public Service. The Siting Board was established primarily to review applications and to issue or deny certificates authorizing the construction and operation of major electric generating facilities. When the Siting Board is reviewing an original application for a certificate, it consists of five permanent members and two ad hoc public members. The five permanent members of the Siting Board also have additional responsibilities to promulgate regulations for the implementation of Article 10, and they have jurisdiction with respect to the amendment, suspension or revocation of a certificate.
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
A. "Public involvement" is the process of enabling the public to participate in decisions that may affect public health, safety and the environment.
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
A. The purposes of a Public Involvement Plan include: (a) providing for an open exchange of information and ideas between the public and the applicant; (b) providing complete information on the application to the public; (c) providing timely notice to the public of important events; (d) providing meaningful public input to key decisions; (e) fostering the active, early and continuing involvement of interested or affected persons; (f) the solicitation of public comments, ideas, and local expertise; and (g) the identification of circumstances and impacts which may not have been known or anticipated by the applicant or government agencies.
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT




PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES

A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.

A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.






A. All municipal and local parties are eligible. The presiding examiner shall reserve at least 50% of the pre-application funds for potential awards to municipalities.

A. The pre-application intervenor funds awarded can be used to defray pre-application expenses incurred by municipal and local parties for expert witnesses, consultants, administrative costs (document preparation and duplications costs) and legal fees. No intervenor funds may be used to pay for judicial review or litigation costs.

PRE-APPLICATION PROCEDURES - STIPULATIONS

A. "Stipulations" are agreements among parties that concern matters before the Siting Board and are designed to simplify or shorten litigation and save costs. Any parties to the proceeding can enter into a stipulation setting forth an agreement on any aspect of the preliminary scoping statement and the scope of studies or program of studies to be conducted. It is often in the interests of applicants and other parties to agree in advance to the content and methodology for conducting studies that will be submitted as part of the application.



APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES





APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.




A. The intervenor funds awarded can be used to defray expenses incurred by municipal and local parties for expert witnesses, consultants, administrative costs (document preparation and duplications costs) and legal fees. No intervenor funds may be used to pay for judicial review or litigation costs.

HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT