Siting Board - Frequently Asked Questions
(click on the blue arrows to expand a question and see the answer)
Expand all sections - Printer Friendly Page
Collapse all sections
BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
A. A "facility" includes all the components of a power plant located on the site and may also include new interconnecting electric power lines and natural gas fuel pipelines. For example, a natural gas-fired facility would include a natural gas pipeline to bring fuel to the facility; a boiler to create steam; a turbine to be rotated by the steam; an electric generator to be turned by the turbine; a cooling system; exhaust stacks; various buildings to house the components; employee areas; back-up fuel storage tanks; ancillary equipment, parking and storage areas; an electric substation including transformers; and a transmission line to carry the electricity out to the grid. A wind-power facility would include wind turbines on towers with integrated electric generators; electric collection lines; access roads; an electric switchyard and substation including transformers; meteorological towers; and a transmission line to carry the electricity out to the grid.
Q. What is meant by the term "certificate"?
A. A "certificate" is a legal document issued by the Siting Board to an applicant if the Siting Board determines that the applicant's proposal to construct and operate a major electric generating facility satisfies the statutory standards set forth in Article 10 of the Public Service Law. The certificate authorizes the applicant to construct and operate the proposed facility. The certificate must be in the form of a written decision and opinion, must include explicit findings and determinations required by the statute, and must state the reasons of the Siting Board for the action taken.
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
A. There is a different procedure depending on whether the facility is proposed to be located (a) in the City of New York; (b) in a town outside of any villages or in a city other than the City of New York; or (c) in a village.
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
A. If such facility is proposed to be located in a town outside of any villages or in a city other than the City of New York, the chief executive officer representing the municipality shall nominate four candidates and the chief executive officer representing the county shall nominate four candidates for consideration. The list of candidates is to be submitted to the President Pro Tem of the Senate or the Speaker of the Assembly within fifteen days of receipt of notification of the pre-application preliminary scoping statement.
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT




PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





A. The presiding examiner will provide for an expedited pre-application funding disbursement schedule to assure early and meaningful public involvement. Following receipt of initial requests for pre-application funds, the presiding examiner shall expeditiously make an initial award of pre-application funds. Subject to the availability of funds, the presiding examiner may fix additional dates for submission of fund requests. Thereafter the presiding examiner may make additional awards of pre-application funds, in relation to the potential for such awards to make an effective contribution to review of the preliminary scoping statement.



PRE-APPLICATION PROCEDURES - STIPULATIONS


A. So that all parties will have an opportunity to participate, the applicant may not commence consultations or seek agreements on proposed stipulations until the pre-application intervenor funds have been allocated by the presiding examiner. Within sixty days of the filing of a preliminary scoping statement, the presiding examiner will convene a meeting of interested parties in order to initiate the stipulation process. The presiding examiner will also oversee the pre-application process and mediate any issue relating to any aspect of the preliminary scoping statement and the methodology and scope of any such studies or programs of study in order to attempt to resolve any questions that may arise.


APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES

A. There are three kinds of parties: (a) automatic statutory parties; (b) parties that have a right to be a party merely by giving notice; and (c) parties that may be permitted to join.




APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.





A. The presiding examiner will award funds on an equitable basis to municipal and local parties who will use them to contribute to a complete record leading to an informed decision as to the appropriateness of the site and the facility and will facilitate broad participation in the proceeding.
HEARING PROCEDURES - CONDUCT OF THE HEARING







SITING BOARD DECISIONS - TIMING OF THE DECISION



SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION



A. The Siting Board must make explicit findings regarding the nature of the probable environmental impacts of the construction and operation of the facility, including the cumulative environmental impacts of the construction and operation of related facilities such as electric lines, gas lines, water supply lines, waste water or other sewage treatment facilities, communications and relay facilities, access roads, rail facilities, or steam lines, including impacts on: (a) ecology, air, ground and surface water, wildlife, and habitat;
(b) public health and safety; (c) cultural, historic, and recreational resources, including aesthetics and scenic values; and (d) transportation, communication, utilities and other infrastructure. Such findings shall include the cumulative impact of emissions on the local community including whether the construction and operation of the facility results in a significant and adverse disproportionate environmental impact, in accordance with regulations promulgated by the Department of Environmental Conservation regarding environmental justice issues.


COMPLIANCE AND ENFORCEMENT