Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
A. An electric generating facility is deemed to be "major" if it has the capacity to generate 25,000 kilowatts (25 megawatts) or more of electricity. The 25 megawatt threshold is roughly equivalent to the average electric power needs of 30,000 households in New York State.
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
A. The five permanent members of the Siting Board are the Chairman of the Department of Public Service who serves as chairperson of the Siting Board; the Commissioner of the Department of Environmental Conservation; the Commissioner of the Department of Health; the Chairperson of the New York State Energy Research and Development Authority; and the Commissioner of Economic Development. The permanent members may designate an alternate to serve instead of the member with respect to all proceedings provided that such designation is in writing and filed with the chairperson.
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
A. To be eligible to be an ad hoc public member, the person must:
(a) be eighteen years of age or older,
(b) be a citizen of the United States;
(c) be a resident of New York State;
(d) be a resident of the municipality in which the facility is proposed to be located (if such facility is proposed to be located within the City of New York, the person must also be a resident of the community district in which the facility is proposed to be located);
(e) not hold another state or local office; and
(f) not retain or hold any official relation to, or any securities of an electric utility corporation operating in the state or proposed for operation in the state, any affiliate thereof or any other company, firm, partnership, corporation, association or joint-stock association that may appear before the Siting Board, nor shall the person have been a director, officer or, within the previous ten years, an employee thereof.
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
A. There is a different procedure depending on whether the facility is proposed to be located (a) in the City of New York; (b) in a town outside of any villages or in a city other than the City of New York; or (c) in a village.
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
A. Candidates from each affected municipality will be nominated.
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
A. Yes, if the facility is excluded because of exemptions (d), (e), (f) or (g) set forth above in the answer to the preceding question, the person intending to construct the major electric generating facility may elect to become subject to the provisions of the Article 10 process.
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT




PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.








PRE-APPLICATION PROCEDURES - STIPULATIONS



A. Yes. Before a stipulation may be executed, notice of the proposed stipulation must be provided and the public and other parties must be afforded a reasonable opportunity to submit comments on the proposed stipulation before it is executed by the interested parties.

APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION



APPLICATION PROCEDURES - DESIGNATION OF PARTIES

A. There are three kinds of parties: (a) automatic statutory parties; (b) parties that have a right to be a party merely by giving notice; and (c) parties that may be permitted to join.




APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES


A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.

A. If the application amendment is deemed a revision requiring substantial additional scrutiny, the applicant will be assessed an additional intervenor fee equal to $1,000 for each 1,000 kilowatts of capacity of the proposed project, as amended, but no more than $75,000.00. The presiding examiner may increase the level of the additional intervenor fee up to the maximum level of $75,000 if the presiding examiner finds circumstances require a higher level of intervenor funding in order to ensure an adequate record.




HEARING PROCEDURES - CONDUCT OF THE HEARING







A. A written transcript record is made of the hearings and of all testimony taken and the cross-examinations thereon. In addition, the presiding examiner will provide a summary of the proceedings in a recommended decision that will be presented to the Siting Board. The parties will also present legal briefs to the Siting Board with citations to the portions of the record they deem relevant to their positions.
SITING BOARD DECISIONS - TIMING OF THE DECISION



A. Yes, but only in an unusual circumstance. If the proceeding is on certain qualifying applications by an owner of an existing major electric generating facility to modify that facility or site a new major electric generating facility adjacent or contiguous to the existing facility, the deadlines are different such that the final decision by the Siting Board must be completed within 6 months, the extension permitted in extraordinary circumstances is 3 months, and the extension permitted to consider a material and substantial amendment to the application is 3 months, unless the deadlines are waived by the applicant.
SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION





COMPLIANCE AND ENFORCEMENT