BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
A. An electric generating facility is deemed to be "major" if it has the capacity to generate 25,000 kilowatts (25 megawatts) or more of electricity. The 25 megawatt threshold is roughly equivalent to the average electric power needs of 30,000 households in New York State.
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
A. If such facility is proposed to be located in the City of New York, the chairperson of the community board, the borough president, and the mayor shall each nominate four candidates for consideration. The list of candidates is to be submitted to the President Pro Tem of the Senate or the Speaker of the Assembly within fifteen days of receipt of notification of the pre-application preliminary scoping statement.
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
A. If such facility is proposed to be located in a village, the chief executive officer representing the town shall nominate four candidates, the chief executive officer representing the county shall nominate four candidates, and the chief executive officer representing the village shall nominate four candidates for consideration. The list of candidates is to be submitted to the President Pro Tem of the Senate or the Speaker of the Assembly within fifteen days of receipt of notification of the pre-application preliminary scoping statement.
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
A. Candidates from each affected municipality will be nominated.
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
A. No. There are three power authorities in New York State: the Power Authority of the State of New York (NYPA); the Green Island Power Authority; and the Long Island Power Authority (LIPA). The statute expressly provides that all three authorities are subject to the provisions of the Article 10 siting process for major electric generating facilities which they build or cause to be built.
Q. Are any electric generating facilities exempt from the Article 10 process?
A. Yes. The statute provides exemption for:
(a) electric generating facilities with a generating capacity of less than 25 megawatts;
(b) electric generating facilities for which the federal government has exclusive siting jurisdiction;
(c) electric generating facilities for which the federal government has concurrent siting jurisdiction and has exercised such jurisdiction to the exclusion of state regulation;
(d) normal repairs, replacements, modifications and improvements of a major electric generating facility, whenever built, which do not constitute a violation of any Article 10 certificate and which do not result in an increase in capacity of the facility of more than 25 megawatts;
(e) electric generating facilities of 200 megawatts or less constructed on lands dedicated to industrial uses where the electricity generated is used solely for industrial purposes on the premises;
(f) electric generating facilities for which an application was made on or before July 12, 2012 for a license, permit, certificate, consent or approval from any federal, state or local commission, agency, board or regulatory body; and.
(g) electric generating facilities under construction on July 12, 2012.
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
A. The Public Involvement Program plan must include: (a) consultation with the affected agencies and other stakeholders; (b) pre-application activities to encourage stakeholders to participate at the earliest opportunity; (c) activities designed to educate the public as to the specific proposal and the Article 10 review process, including the availability of funding for municipal and local parties; (d) the establishment of a website to disseminate information to the public; (e) notifications; and (f) activities designed to encourage participation by stakeholders in the certification and compliance process. In addition, an applicant is expected to communicate with the public early in the pre-application process through the use of various means such as media coverage, direct mailings, fliers or newsletters. This should be done before any agreements on project stipulations have been made between the applicant and interested parties. In addition, the applicant is expected to hold public meetings, offer presentations to individual groups and organizations, and establish a community presence. Establishing a local office, a toll-free telephone number, Internet website, or a community advisory group are among the actions an applicant may take to establish its presence in the community. An applicant should disseminate information about its proposed project at meetings, in mass mailings and through local media.
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
A. DPS has 30 days after the date of the applicant's submittal to make written comments on the adequacy of the Public Involvement Program plan. If deemed inadequate, DPS will make specific written recommendations as to what measures are necessary to make the Public Involvement Program plan adequate. Thereafter, the applicant has 30 days to consider the measures recommended by DPS and, in a final written Public Involvement Program plan filed with the Secretary, shall as to each specific measure either revise the Public Involvement Program plan to incorporate the DPS recommendation, or provide a written explanation as to why the applicant is not incorporating the DPS recommendation.
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT
Q. What is a Preliminary Scoping Statement?
Q. When does the Preliminary Scoping Statement have to be filed?
Q. What kind of information must be included in a Preliminary Scoping Statement?
Q. What happens after the Preliminary Scoping Statement is filed?
PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the fund for municipal and local parties?
A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.
Q: How does an applicant set up the fund?
A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.
Q. What is an "intervenor"?
Q. What is the amount of the intervenor fee assessed during the pre-application stage?
A. Applicants submitting a preliminary scoping statement are assessed an intervenor fee equal to $350 for each 1,000 kilowatts (1 megawatt) of generating capacity of the subject facility, but no more than $200,000. For example, for a 100 megawatt facility, the pre-application intervenor fee would be $35,000 (100 x $350).
Q. What happens if after the pre-application intervenor fees have been used up, the applicant amends its preliminary scoping statement and more review is required?
Q. How does a qualified intervenor make a request for intervenor funds?
Q. When are pre-application intervenor funds awarded?
Q. Who is eligible for intervenor funds?
A. All municipal and local parties are eligible. The presiding examiner shall reserve at least 50% of the pre-application funds for potential awards to municipalities.
Q. What can pre-application intervenor funds be used for?
Q. On what basis will the funds be awarded?
PRE-APPLICATION PROCEDURES - STIPULATIONS
Q. What are stipulations?
A. "Stipulations" are agreements among parties that concern matters before the Siting Board and are designed to simplify or shorten litigation and save costs. Any parties to the proceeding can enter into a stipulation setting forth an agreement on any aspect of the preliminary scoping statement and the scope of studies or program of studies to be conducted. It is often in the interests of applicants and other parties to agree in advance to the content and methodology for conducting studies that will be submitted as part of the application.
Q. How is the stipulations process initiated?
Q. Do other parties and the public get an opportunity to participate in the stipulations process?
A. Yes. Before a stipulation may be executed, notice of the proposed stipulation must be provided and the public and other parties must be afforded a reasonable opportunity to submit comments on the proposed stipulation before it is executed by the interested parties.
Q. What happens if a party does not agree that a stipulation entered into between the applicant and another party is adequate?
APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION
Q. What happens when an Article 10 application is submitted?
Q. What happens if the documents submitted are insufficient to comply with the requirements of the law, regulations and stipulations?
Q. What happens if the documents submitted are sufficient to comply with the requirements of the law, regulations and stipulations?
APPLICATION PROCEDURES - DESIGNATION OF PARTIES
Q. Who are the parties to an Article 10 proceeding?
Q. Who are the automatic statutory parties to an Article 10 proceeding?
Q. Who are the parties that have a right to be a party to an Article 10 proceeding merely by giving notice?
A. Provided they file with the Siting Board a notice of intent to be a party, within 45 days after the date given in the published notice as the date for the filing of the application, the following parties have a right to be a party to an Article 10 proceeding merely by giving the required notice: (a) the affected municipality; (b) any individual resident of an affected municipality; (c) any non-profit corporation or association, formed in whole or in part to promote conservation or natural beauty, to protect the environment, personal health or other biological values, to preserve historical sites, to promote consumer interests, to represent commercial and industrial groups or to promote the orderly development of any area in which the facility is to be located; and (d) any other municipality or resident of such municipality located within a five mile radius of such proposed facility
(their notice of intent must include an explanation of the potential environmental effects on such municipality or person). In addition, the presiding officer may for good cause shown permit a municipality or other person to become a party and to participate in all subsequent stages of the proceeding.
Q. Who are the parties that may be permitted to join?
Q. Where does a party file a notice of intent to be a party?
A. A notice of intent to be a party must be filed with the Secretary to the Siting Board.
APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the amount of the intervenor fee assessed when an application is filed?
Q. How does an applicant set up the fund?
Q. What happens if after the application phase intervenor fees have been used up, the applicant amends its application and more review is required?
Q. How does a qualified intervenor make a request for intervenor funds?
Q. Who is eligible for intervenor funds?
A. All municipal and local parties to the proceeding are eligible for application phase intervenor funds. The presiding examiner shall reserve at least 50% of the application phase funds for potential awards to municipalities.
Q. What can application phase intervenor funds be used for?
Q. On what basis will the funds be awarded?
HEARING PROCEDURES - CONDUCT OF THE HEARING
Q. Who conducts the hearings?
Q. What kinds of hearings will be held?
A. It is expected that both public statement hearings and trial-type evidentiary hearings will be held. In addition, persons are permitted to make a limited appearance.
Q. What are "public statement" hearings?
Q. What is a "limited appearance"?
A. Any person may make a limited appearance in the proceeding by filing a statement of his or her intent to limit his or her appearance in writing at any time prior to the commencement of the hearing. All papers and matters filed by a person making a limited appearance shall become part of the record. No person making a limited appearance shall be a party or shall have the right to present testimony or cross-examine witnesses or parties.
Q. What are "trial-type evidentiary" hearings?
Q. What is "discovery"?
Q. If the Siting Board does not personally conduct the hearings, how does it become informed of the proceedings?
SITING BOARD DECISIONS - TIMING OF THE DECISION
Q. Is there a deadline by which the Siting Board must make a final decision on an Article 10 application?
Q. What happens to the deadline if the application is amended during the Article 10 proceeding?
Q. Are there any other exceptions to the deadlines described above?
SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION
Q. What options does the Siting Board have in making a decision on an Article 10 application?
Q. What substantive matters must be addressed in any Siting Board decision to grant an Article 10 certificate?
Q. What are the required statutory findings that must be made by the Siting Board?
Q. What are the required statutory determinations that must be made by the Siting Board?
Q. What are the required statutory factors that must be considered by the Siting Board in making the required determinations?
COMPLIANCE AND ENFORCEMENT
Q. Who is in charge of compliance and enforcement matters regarding a Certificate that has been issued?