Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
A. An electric generating facility is deemed to be "major" if it has the capacity to generate 25,000 kilowatts (25 megawatts) or more of electricity. The 25 megawatt threshold is roughly equivalent to the average electric power needs of 30,000 households in New York State.
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
A. "Ad hoc" is a Latin term meaning "for this special purpose". Two ad hoc members will be appointed for the special purpose of providing a local voice in each proceeding conducted to consider specific individual applications for certificates. Each facility application will have its own associated ad hoc members.
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
A. To be eligible to be an ad hoc public member, the person must:
(a) be eighteen years of age or older,
(b) be a citizen of the United States;
(c) be a resident of New York State;
(d) be a resident of the municipality in which the facility is proposed to be located (if such facility is proposed to be located within the City of New York, the person must also be a resident of the community district in which the facility is proposed to be located);
(e) not hold another state or local office; and
(f) not retain or hold any official relation to, or any securities of an electric utility corporation operating in the state or proposed for operation in the state, any affiliate thereof or any other company, firm, partnership, corporation, association or joint-stock association that may appear before the Siting Board, nor shall the person have been a director, officer or, within the previous ten years, an employee thereof.
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
A. If such facility is proposed to be located in a town outside of any villages or in a city other than the City of New York, the chief executive officer representing the municipality shall nominate four candidates and the chief executive officer representing the county shall nominate four candidates for consideration. The list of candidates is to be submitted to the President Pro Tem of the Senate or the Speaker of the Assembly within fifteen days of receipt of notification of the pre-application preliminary scoping statement.
Q. How is the list of candidates established in a village?
A. If such facility is proposed to be located in a village, the chief executive officer representing the town shall nominate four candidates, the chief executive officer representing the county shall nominate four candidates, and the chief executive officer representing the village shall nominate four candidates for consideration. The list of candidates is to be submitted to the President Pro Tem of the Senate or the Speaker of the Assembly within fifteen days of receipt of notification of the pre-application preliminary scoping statement.
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
A. No. There are three power authorities in New York State: the Power Authority of the State of New York (NYPA); the Green Island Power Authority; and the Long Island Power Authority (LIPA). The statute expressly provides that all three authorities are subject to the provisions of the Article 10 siting process for major electric generating facilities which they build or cause to be built.
Q. Are any electric generating facilities exempt from the Article 10 process?
A. Yes. The statute provides exemption for:
(a) electric generating facilities with a generating capacity of less than 25 megawatts;
(b) electric generating facilities for which the federal government has exclusive siting jurisdiction;
(c) electric generating facilities for which the federal government has concurrent siting jurisdiction and has exercised such jurisdiction to the exclusion of state regulation;
(d) normal repairs, replacements, modifications and improvements of a major electric generating facility, whenever built, which do not constitute a violation of any Article 10 certificate and which do not result in an increase in capacity of the facility of more than 25 megawatts;
(e) electric generating facilities of 200 megawatts or less constructed on lands dedicated to industrial uses where the electricity generated is used solely for industrial purposes on the premises;
(f) electric generating facilities for which an application was made on or before July 12, 2012 for a license, permit, certificate, consent or approval from any federal, state or local commission, agency, board or regulatory body; and.
(g) electric generating facilities under construction on July 12, 2012.
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
A. At the earliest stage of the Article 10 process, applicants are required to prepare and begin implementing a Public Involvement Program. In addition, to ensure that the public and interested parties are fully assisted and advised in participating in the Article 10 process,
an Office of Public Information Coordinator has been created within the New York State Department of Public Service.
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
A. The Public Involvement Program plan must include: (a) consultation with the affected agencies and other stakeholders; (b) pre-application activities to encourage stakeholders to participate at the earliest opportunity; (c) activities designed to educate the public as to the specific proposal and the Article 10 review process, including the availability of funding for municipal and local parties; (d) the establishment of a website to disseminate information to the public; (e) notifications; and (f) activities designed to encourage participation by stakeholders in the certification and compliance process. In addition, an applicant is expected to communicate with the public early in the pre-application process through the use of various means such as media coverage, direct mailings, fliers or newsletters. This should be done before any agreements on project stipulations have been made between the applicant and interested parties. In addition, the applicant is expected to hold public meetings, offer presentations to individual groups and organizations, and establish a community presence. Establishing a local office, a toll-free telephone number, Internet website, or a community advisory group are among the actions an applicant may take to establish its presence in the community. An applicant should disseminate information about its proposed project at meetings, in mass mailings and through local media.
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT
Q. What is a Preliminary Scoping Statement?
Q. When does the Preliminary Scoping Statement have to be filed?
A. The preliminary scoping statement must be filed no less than 90 days before the date on which the applicant files its application for an Article 10 certificate. In addition, at least three days before the preliminary scoping statement is filed, the applicant must publish a public notice and summary of the preliminary scoping statement in local newspapers in the affected area and serve a copy of the notice and summary upon public officials and all persons who requested to receive such notices.
Q. What kind of information must be included in a Preliminary Scoping Statement?
Q. What happens after the Preliminary Scoping Statement is filed?
PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the fund for municipal and local parties?
A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.
Q: How does an applicant set up the fund?
A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.
Q. What is an "intervenor"?
Q. What is the amount of the intervenor fee assessed during the pre-application stage?
A. Applicants submitting a preliminary scoping statement are assessed an intervenor fee equal to $350 for each 1,000 kilowatts (1 megawatt) of generating capacity of the subject facility, but no more than $200,000. For example, for a 100 megawatt facility, the pre-application intervenor fee would be $35,000 (100 x $350).
Q. What happens if after the pre-application intervenor fees have been used up, the applicant amends its preliminary scoping statement and more review is required?
Q. How does a qualified intervenor make a request for intervenor funds?
Q. When are pre-application intervenor funds awarded?
Q. Who is eligible for intervenor funds?
Q. What can pre-application intervenor funds be used for?
Q. On what basis will the funds be awarded?
PRE-APPLICATION PROCEDURES - STIPULATIONS
Q. What are stipulations?
Q. How is the stipulations process initiated?
Q. Do other parties and the public get an opportunity to participate in the stipulations process?
Q. What happens if a party does not agree that a stipulation entered into between the applicant and another party is adequate?
APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION
Q. What happens when an Article 10 application is submitted?
Q. What happens if the documents submitted are insufficient to comply with the requirements of the law, regulations and stipulations?
Q. What happens if the documents submitted are sufficient to comply with the requirements of the law, regulations and stipulations?
APPLICATION PROCEDURES - DESIGNATION OF PARTIES
Q. Who are the parties to an Article 10 proceeding?
Q. Who are the automatic statutory parties to an Article 10 proceeding?
A. The applicant, staff of the Department of Public Service, the Department of Environmental Conservation, the Department of Economic Development, the Department of Health, the Department of Agriculture and Markets, the New York State Energy Research and Development Authority, the Department of State, the Office of Parks, Recreation and Historic Preservation, and in certain instances, the Adirondack Park Agency.
Q. Who are the parties that have a right to be a party to an Article 10 proceeding merely by giving notice?
Q. Who are the parties that may be permitted to join?
Q. Where does a party file a notice of intent to be a party?
APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the amount of the intervenor fee assessed when an application is filed?
Q. How does an applicant set up the fund?
A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.
Q. What happens if after the application phase intervenor fees have been used up, the applicant amends its application and more review is required?
A. If the application amendment is deemed a revision requiring substantial additional scrutiny, the applicant will be assessed an additional intervenor fee equal to $1,000 for each 1,000 kilowatts of capacity of the proposed project, as amended, but no more than $75,000.00. The presiding examiner may increase the level of the additional intervenor fee up to the maximum level of $75,000 if the presiding examiner finds circumstances require a higher level of intervenor funding in order to ensure an adequate record.
Q. How does a qualified intervenor make a request for intervenor funds?
A. A notice of availability of the funds will be issued providing a schedule and related information. The notice will describe how municipal and local parties may apply for intervenor funds. Requests must be submitted to the presiding examiner within 30 days after the issuance of the notice by filing the request with the Secretary and submitting a copy to the presiding examiner and to the other parties to the proceeding. At any pre-hearing conference that may be held to consider fund requests, the parties should be prepared to discuss their funding applications and the award of funds. Parties are encouraged to consider consolidating their requests with similar funding proposals made by other parties.
Q. Who is eligible for intervenor funds?
Q. What can application phase intervenor funds be used for?
Q. On what basis will the funds be awarded?
A. The presiding examiner will award funds on an equitable basis to municipal and local parties who will use them to contribute to a complete record leading to an informed decision as to the appropriateness of the site and the facility and will facilitate broad participation in the proceeding.
HEARING PROCEDURES - CONDUCT OF THE HEARING
Q. Who conducts the hearings?
A. The hearings will be conducted by a presiding examiner designated by the Department of Public Service. An associate examiner shall be designated by the Department of Environmental Conservation. The associate examiner will assist the presiding examiner in inquiring into and calling for testimony concerning relevant and material matters, and the conclusions and recommendations of the associate examiner will be incorporated in the recommended decision of the presiding examiner.
Q. What kinds of hearings will be held?
Q. What are "public statement" hearings?
Q. What is a "limited appearance"?
Q. What are "trial-type evidentiary" hearings?
A. Trial-type evidentiary hearings are designed to obtain sworn testimony from witnesses (usually expert witnesses) that are subject to cross examination by the parties to the proceeding. The format is designed like a trial and it is recommended that the participants be assisted by legal counsel, although the assistance of legal counsel is not mandatory. The usual practice is for written direct and rebuttal testimony and discovery to be circulated to the parties in advance so that the hearings can focus on the cross examination of witnesses.
Q. What is "discovery"?
Q. If the Siting Board does not personally conduct the hearings, how does it become informed of the proceedings?
SITING BOARD DECISIONS - TIMING OF THE DECISION
Q. Is there a deadline by which the Siting Board must make a final decision on an Article 10 application?
Q. What happens to the deadline if the application is amended during the Article 10 proceeding?
Q. Are there any other exceptions to the deadlines described above?
SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION
Q. What options does the Siting Board have in making a decision on an Article 10 application?
Q. What substantive matters must be addressed in any Siting Board decision to grant an Article 10 certificate?
Q. What are the required statutory findings that must be made by the Siting Board?
Q. What are the required statutory determinations that must be made by the Siting Board?
Q. What are the required statutory factors that must be considered by the Siting Board in making the required determinations?
COMPLIANCE AND ENFORCEMENT