BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
A. There is a different procedure depending on whether the facility is proposed to be located (a) in the City of New York; (b) in a town outside of any villages or in a city other than the City of New York; or (c) in a village.
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
A. If such facility is proposed to be located in a village, the chief executive officer representing the town shall nominate four candidates, the chief executive officer representing the county shall nominate four candidates, and the chief executive officer representing the village shall nominate four candidates for consideration. The list of candidates is to be submitted to the President Pro Tem of the Senate or the Speaker of the Assembly within fifteen days of receipt of notification of the pre-application preliminary scoping statement.
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
A. The Department of Public Service provides a presiding examiner and whatever legal, technological, scientific, engineering and other services that may be required. The Department of Environmental Conservation provides an associate examiner. The Secretary and the General Counsel to the Public Service Commission serve as Secretary and the General Counsel to the Siting Board.
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
A. Yes. The statute provides exemption for:
(a) electric generating facilities with a generating capacity of less than 25 megawatts;
(b) electric generating facilities for which the federal government has exclusive siting jurisdiction;
(c) electric generating facilities for which the federal government has concurrent siting jurisdiction and has exercised such jurisdiction to the exclusion of state regulation;
(d) normal repairs, replacements, modifications and improvements of a major electric generating facility, whenever built, which do not constitute a violation of any Article 10 certificate and which do not result in an increase in capacity of the facility of more than 25 megawatts;
(e) electric generating facilities of 200 megawatts or less constructed on lands dedicated to industrial uses where the electricity generated is used solely for industrial purposes on the premises;
(f) electric generating facilities for which an application was made on or before July 12, 2012 for a license, permit, certificate, consent or approval from any federal, state or local commission, agency, board or regulatory body; and.
(g) electric generating facilities under construction on July 12, 2012.
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
A. At the earliest stage of the Article 10 process, applicants are required to prepare and begin implementing a Public Involvement Program. In addition, to ensure that the public and interested parties are fully assisted and advised in participating in the Article 10 process,
an Office of Public Information Coordinator has been created within the New York State Department of Public Service.
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
A. The purposes of a Public Involvement Plan include: (a) providing for an open exchange of information and ideas between the public and the applicant; (b) providing complete information on the application to the public; (c) providing timely notice to the public of important events; (d) providing meaningful public input to key decisions; (e) fostering the active, early and continuing involvement of interested or affected persons; (f) the solicitation of public comments, ideas, and local expertise; and (g) the identification of circumstances and impacts which may not have been known or anticipated by the applicant or government agencies.
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT
Q. What is a Preliminary Scoping Statement?
Q. When does the Preliminary Scoping Statement have to be filed?
Q. What kind of information must be included in a Preliminary Scoping Statement?
Q. What happens after the Preliminary Scoping Statement is filed?
A. Within 21 days after the filing of the preliminary scoping statement, any person, agency or municipality may submit comments on the preliminary scoping statement by serving such comments on the applicant and filing a copy with the secretary. Within 21 days after the closing of the comment period, the applicant shall prepare a summary of the material comments and its reply thereto, and file and serve its summary of comments and its reply in the same manner as it files and serves the preliminary scoping statement. Thereafter, it is expected that the applicant will work with interested parties to resolve any disagreements they may have about the sufficiency of the planned scope and methodology of studies to be included in the application.
PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the fund for municipal and local parties?
Q: How does an applicant set up the fund?
A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.
Q. What is an "intervenor"?
Q. What is the amount of the intervenor fee assessed during the pre-application stage?
Q. What happens if after the pre-application intervenor fees have been used up, the applicant amends its preliminary scoping statement and more review is required?
Q. How does a qualified intervenor make a request for intervenor funds?
Q. When are pre-application intervenor funds awarded?
Q. Who is eligible for intervenor funds?
Q. What can pre-application intervenor funds be used for?
A. The pre-application intervenor funds awarded can be used
to defray pre-application expenses incurred by municipal and local parties for expert witnesses, consultants, administrative costs (document preparation and duplications costs) and legal fees.
No intervenor funds may be used to pay for judicial review or litigation costs.
Q. On what basis will the funds be awarded?
A. The presiding examiner will award funds on an equitable basis to participants during the pre-application phase to be used to make an effective contribution to review of the preliminary scoping statement, and thereby provide early and effective public involvement.
PRE-APPLICATION PROCEDURES - STIPULATIONS
Q. What are stipulations?
Q. How is the stipulations process initiated?
Q. Do other parties and the public get an opportunity to participate in the stipulations process?
Q. What happens if a party does not agree that a stipulation entered into between the applicant and another party is adequate?
APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION
Q. What happens when an Article 10 application is submitted?
A. Within sixty days of receipt, the Chairperson of the Siting Board determines whether the documents submitted comply with the requirements of the law, regulations and stipulations. The Department of Environmental Conservation also advises the Siting Board within the sixty day period whether the documents submitted contain sufficient information.
Q. What happens if the documents submitted are insufficient to comply with the requirements of the law, regulations and stipulations?
A. If the documents submitted are insufficient to comply with the requirements of the law, regulations and stipulations, the Chairperson of the Siting Board will issue a letter to the applicant advising of the deficiencies that must be corrected before the documents can be deemed a complying application.
The Chairperson of the Siting Board may also require the filing of any additional information needed to supplement an application before or during the hearings.
Q. What happens if the documents submitted are sufficient to comply with the requirements of the law, regulations and stipulations?
A. If the documents submitted are sufficient to comply with the requirements of the law, regulations and stipulations, the Chairperson of the Siting Board will issue a letter to the applicant advising that the documents submitted constitute a complying application. The Chairperson will also fix the date for the commencement of a public hearing and the Department of Environmental Conservation will initiate its review pursuant to federally delegated or approved environmental permitting authority or air and water permit applications. Within a reasonable time, the presiding examiner will hold a prehearing conference to expedite the orderly conduct and completion of the hearing, to specify the issues, to obtain stipulations as to matters not disputed, and to deal with other matters deemed appropriate. The presiding examiner will then issue an order identifying the issues to be addressed by the parties. Later in the proceeding there may also be a consideration of additional issues which warrant consideration in order to develop an adequate record.
APPLICATION PROCEDURES - DESIGNATION OF PARTIES
Q. Who are the parties to an Article 10 proceeding?
Q. Who are the automatic statutory parties to an Article 10 proceeding?
A. The applicant, staff of the Department of Public Service, the Department of Environmental Conservation, the Department of Economic Development, the Department of Health, the Department of Agriculture and Markets, the New York State Energy Research and Development Authority, the Department of State, the Office of Parks, Recreation and Historic Preservation, and in certain instances, the Adirondack Park Agency.
Q. Who are the parties that have a right to be a party to an Article 10 proceeding merely by giving notice?
A. Provided they file with the Siting Board a notice of intent to be a party, within 45 days after the date given in the published notice as the date for the filing of the application, the following parties have a right to be a party to an Article 10 proceeding merely by giving the required notice: (a) the affected municipality; (b) any individual resident of an affected municipality; (c) any non-profit corporation or association, formed in whole or in part to promote conservation or natural beauty, to protect the environment, personal health or other biological values, to preserve historical sites, to promote consumer interests, to represent commercial and industrial groups or to promote the orderly development of any area in which the facility is to be located; and (d) any other municipality or resident of such municipality located within a five mile radius of such proposed facility
(their notice of intent must include an explanation of the potential environmental effects on such municipality or person). In addition, the presiding officer may for good cause shown permit a municipality or other person to become a party and to participate in all subsequent stages of the proceeding.
Q. Who are the parties that may be permitted to join?
Q. Where does a party file a notice of intent to be a party?
A. A notice of intent to be a party must be filed with the Secretary to the Siting Board.
APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the amount of the intervenor fee assessed when an application is filed?
A. Applicants are assessed an intervenor fee equal to $1,000 for each 1,000 kilowatts (1 megawatt) of generating capacity of the subject facility, but no more than $400,000. For example, for a 100 megawatt facility, the application phase intervenor fee would be $100,000 (100 x $1000). In addition, for facilities that will require storage or disposal of fuel waste byproduct, an additional intervenor fee will be assessed at the application phase of $500.00 for each 1,000 kilowatts (1 megawatt) of capacity, but no more than an additional $50,000.00.
Q. How does an applicant set up the fund?
A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.
Q. What happens if after the application phase intervenor fees have been used up, the applicant amends its application and more review is required?
Q. How does a qualified intervenor make a request for intervenor funds?
A. A notice of availability of the funds will be issued providing a schedule and related information. The notice will describe how municipal and local parties may apply for intervenor funds. Requests must be submitted to the presiding examiner within 30 days after the issuance of the notice by filing the request with the Secretary and submitting a copy to the presiding examiner and to the other parties to the proceeding. At any pre-hearing conference that may be held to consider fund requests, the parties should be prepared to discuss their funding applications and the award of funds. Parties are encouraged to consider consolidating their requests with similar funding proposals made by other parties.
Q. Who is eligible for intervenor funds?
Q. What can application phase intervenor funds be used for?
Q. On what basis will the funds be awarded?
HEARING PROCEDURES - CONDUCT OF THE HEARING
Q. Who conducts the hearings?
Q. What kinds of hearings will be held?
Q. What are "public statement" hearings?
A. Public statement hearings are designed to obtain input from the general public. The format is designed for the taking of unsworn oral statements, although written statements ordinarily may also be submitted. Parties to the proceeding are not permitted to cross examine the persons making such statements.
Q. What is a "limited appearance"?
Q. What are "trial-type evidentiary" hearings?
A. Trial-type evidentiary hearings are designed to obtain sworn testimony from witnesses (usually expert witnesses) that are subject to cross examination by the parties to the proceeding. The format is designed like a trial and it is recommended that the participants be assisted by legal counsel, although the assistance of legal counsel is not mandatory. The usual practice is for written direct and rebuttal testimony and discovery to be circulated to the parties in advance so that the hearings can focus on the cross examination of witnesses.
Q. What is "discovery"?
Q. If the Siting Board does not personally conduct the hearings, how does it become informed of the proceedings?
SITING BOARD DECISIONS - TIMING OF THE DECISION
Q. Is there a deadline by which the Siting Board must make a final decision on an Article 10 application?
Q. What happens to the deadline if the application is amended during the Article 10 proceeding?
Q. Are there any other exceptions to the deadlines described above?
SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION
Q. What options does the Siting Board have in making a decision on an Article 10 application?
A. The Siting Board can grant a certificate in the manner requested by the applicant, it can grant a certificate subject to modifications and or conditions, or it may deny the application. In rendering a decision on an application for a certificate, the Siting Board must issue a written opinion stating its reasons for the action taken.
Q. What substantive matters must be addressed in any Siting Board decision to grant an Article 10 certificate?
A. The Siting Board is required to make certain statutory findings and determinations, and the required determinations can only be made after considering certain required factors.
Q. What are the required statutory findings that must be made by the Siting Board?
A. The Siting Board must make explicit findings regarding the nature of the probable environmental impacts of the construction and operation of the facility, including the cumulative environmental impacts of the construction and operation of related facilities such as electric lines, gas lines, water supply lines, waste water or other sewage treatment facilities, communications and relay facilities, access roads, rail facilities, or steam lines, including impacts on: (a) ecology, air, ground and surface water, wildlife, and habitat;
(b) public health and safety; (c) cultural, historic, and recreational resources, including aesthetics and scenic values; and (d) transportation, communication, utilities and other infrastructure. Such findings shall include the cumulative impact of emissions on the local community including whether the construction and operation of the facility results in a significant and adverse disproportionate environmental impact, in accordance with regulations promulgated by the Department of Environmental Conservation regarding environmental justice issues.
Q. What are the required statutory determinations that must be made by the Siting Board?
Q. What are the required statutory factors that must be considered by the Siting Board in making the required determinations?
COMPLIANCE AND ENFORCEMENT
Q. Who is in charge of compliance and enforcement matters regarding a Certificate that has been issued?