BASIC CONCEPTS
Q. What is Article 10?
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
A. "Ad hoc" is a Latin term meaning "for this special purpose". Two ad hoc members will be appointed for the special purpose of providing a local voice in each proceeding conducted to consider specific individual applications for certificates. Each facility application will have its own associated ad hoc members.
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
A. Yes. The ad hoc appointees shall receive the sum of two hundred dollars for each day in which they are actually engaged in the performance of their duties plus actual and necessary expenses incurred by them in the performance of such duties.
Q. What are the qualifications to be an ad hoc public member?
A. To be eligible to be an ad hoc public member, the person must:
(a) be eighteen years of age or older,
(b) be a citizen of the United States;
(c) be a resident of New York State;
(d) be a resident of the municipality in which the facility is proposed to be located (if such facility is proposed to be located within the City of New York, the person must also be a resident of the community district in which the facility is proposed to be located);
(e) not hold another state or local office; and
(f) not retain or hold any official relation to, or any securities of an electric utility corporation operating in the state or proposed for operation in the state, any affiliate thereof or any other company, firm, partnership, corporation, association or joint-stock association that may appear before the Siting Board, nor shall the person have been a director, officer or, within the previous ten years, an employee thereof.
Q. How are the two ad hoc public members designated to serve on the Siting Board?
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
A. Candidates from each affected municipality will be nominated.
Q. What resources are available to assist the Siting Board?
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
A. "Public involvement" is the process of enabling the public to participate in decisions that may affect public health, safety and the environment.
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
Q. How is public involvement conducted?
Q. Is the public required to participate in the applicant's public involvement activities?
A. It is the Siting Board’s policy to encourage public participation in the review of the applicant’s proposal at the earliest opportunity so that public input can be considered.
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
A. The Public Involvement Program plan must include: (a) consultation with the affected agencies and other stakeholders; (b) pre-application activities to encourage stakeholders to participate at the earliest opportunity; (c) activities designed to educate the public as to the specific proposal and the Article 10 review process, including the availability of funding for municipal and local parties; (d) the establishment of a website to disseminate information to the public; (e) notifications; and (f) activities designed to encourage participation by stakeholders in the certification and compliance process. In addition, an applicant is expected to communicate with the public early in the pre-application process through the use of various means such as media coverage, direct mailings, fliers or newsletters. This should be done before any agreements on project stipulations have been made between the applicant and interested parties. In addition, the applicant is expected to hold public meetings, offer presentations to individual groups and organizations, and establish a community presence. Establishing a local office, a toll-free telephone number, Internet website, or a community advisory group are among the actions an applicant may take to establish its presence in the community. An applicant should disseminate information about its proposed project at meetings, in mass mailings and through local media.
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
A. In such a situation, parties would be free to seek procedural and substantive remedies in the Article 10 process.
Q. How do people who do not speak English participate in public involvement?
A. Applicants are required to identify significant non-English speaking populations and to address the need for non-English communication and participation in their Public Involvement Program plan.
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
A. The Office of Public Information Coordinator assists the public and interested parties by: (a) implementing measures that assure public participation in matters before the Siting Board; (b) responding to inquiries from the public for information on how to participate; (c) assisting the public in requesting records; (d) ensuring all interested persons are provided with a reasonable opportunity to participate at public meetings; (e) ensuring that all necessary or required documents are available for public access on the Siting Board website; and (f) any other duties as may be prescribed by the Siting Board, after consultation with the Department of Public Service.
Q. What is the Department of Public Service?
A. The New York State Department of Public Service is one of 20 major departments in New York State government. The Siting Board is a decision-making body organized within the Department of Public Service. The Public Service Commission is another decision-making body organized within the Department of Public Service. The Chairman of the Public Service Commission also serves as chief executive of the Department of Public Service and Chairperson of the Siting Board. The staff of the Department of Public Service represent the public interest in all Siting Board proceedings, under the direction of the Chairperson.
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT
Q. What is a Preliminary Scoping Statement?
Q. When does the Preliminary Scoping Statement have to be filed?
Q. What kind of information must be included in a Preliminary Scoping Statement?
Q. What happens after the Preliminary Scoping Statement is filed?
PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the fund for municipal and local parties?
A. Applicants are required at several stages in the Article 10 process to provide funds to be used to defray certain expenses incurred by municipal and local parties when participating in an Article 10 proceeding. These funds are known as "intervenor" funds collected by assessing an "intervenor" fee on the applicant.
Q: How does an applicant set up the fund?
Q. What is an "intervenor"?
Q. What is the amount of the intervenor fee assessed during the pre-application stage?
A. Applicants submitting a preliminary scoping statement are assessed an intervenor fee equal to $350 for each 1,000 kilowatts (1 megawatt) of generating capacity of the subject facility, but no more than $200,000. For example, for a 100 megawatt facility, the pre-application intervenor fee would be $35,000 (100 x $350).
Q. What happens if after the pre-application intervenor fees have been used up, the applicant amends its preliminary scoping statement and more review is required?
Q. How does a qualified intervenor make a request for intervenor funds?
Q. When are pre-application intervenor funds awarded?
Q. Who is eligible for intervenor funds?
Q. What can pre-application intervenor funds be used for?
Q. On what basis will the funds be awarded?
PRE-APPLICATION PROCEDURES - STIPULATIONS
Q. What are stipulations?
Q. How is the stipulations process initiated?
Q. Do other parties and the public get an opportunity to participate in the stipulations process?
Q. What happens if a party does not agree that a stipulation entered into between the applicant and another party is adequate?
APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION
Q. What happens when an Article 10 application is submitted?
A. Within sixty days of receipt, the Chairperson of the Siting Board determines whether the documents submitted comply with the requirements of the law, regulations and stipulations. The Department of Environmental Conservation also advises the Siting Board within the sixty day period whether the documents submitted contain sufficient information.
Q. What happens if the documents submitted are insufficient to comply with the requirements of the law, regulations and stipulations?
Q. What happens if the documents submitted are sufficient to comply with the requirements of the law, regulations and stipulations?
APPLICATION PROCEDURES - DESIGNATION OF PARTIES
Q. Who are the parties to an Article 10 proceeding?
Q. Who are the automatic statutory parties to an Article 10 proceeding?
A. The applicant, staff of the Department of Public Service, the Department of Environmental Conservation, the Department of Economic Development, the Department of Health, the Department of Agriculture and Markets, the New York State Energy Research and Development Authority, the Department of State, the Office of Parks, Recreation and Historic Preservation, and in certain instances, the Adirondack Park Agency.
Q. Who are the parties that have a right to be a party to an Article 10 proceeding merely by giving notice?
Q. Who are the parties that may be permitted to join?
Q. Where does a party file a notice of intent to be a party?
APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the amount of the intervenor fee assessed when an application is filed?
A. Applicants are assessed an intervenor fee equal to $1,000 for each 1,000 kilowatts (1 megawatt) of generating capacity of the subject facility, but no more than $400,000. For example, for a 100 megawatt facility, the application phase intervenor fee would be $100,000 (100 x $1000). In addition, for facilities that will require storage or disposal of fuel waste byproduct, an additional intervenor fee will be assessed at the application phase of $500.00 for each 1,000 kilowatts (1 megawatt) of capacity, but no more than an additional $50,000.00.
Q. How does an applicant set up the fund?
Q. What happens if after the application phase intervenor fees have been used up, the applicant amends its application and more review is required?
A. If the application amendment is deemed a revision requiring substantial additional scrutiny, the applicant will be assessed an additional intervenor fee equal to $1,000 for each 1,000 kilowatts of capacity of the proposed project, as amended, but no more than $75,000.00. The presiding examiner may increase the level of the additional intervenor fee up to the maximum level of $75,000 if the presiding examiner finds circumstances require a higher level of intervenor funding in order to ensure an adequate record.
Q. How does a qualified intervenor make a request for intervenor funds?
A. A notice of availability of the funds will be issued providing a schedule and related information. The notice will describe how municipal and local parties may apply for intervenor funds. Requests must be submitted to the presiding examiner within 30 days after the issuance of the notice by filing the request with the Secretary and submitting a copy to the presiding examiner and to the other parties to the proceeding. At any pre-hearing conference that may be held to consider fund requests, the parties should be prepared to discuss their funding applications and the award of funds. Parties are encouraged to consider consolidating their requests with similar funding proposals made by other parties.
Q. Who is eligible for intervenor funds?
Q. What can application phase intervenor funds be used for?
Q. On what basis will the funds be awarded?
HEARING PROCEDURES - CONDUCT OF THE HEARING
Q. Who conducts the hearings?
A. The hearings will be conducted by a presiding examiner designated by the Department of Public Service. An associate examiner shall be designated by the Department of Environmental Conservation. The associate examiner will assist the presiding examiner in inquiring into and calling for testimony concerning relevant and material matters, and the conclusions and recommendations of the associate examiner will be incorporated in the recommended decision of the presiding examiner.
Q. What kinds of hearings will be held?
Q. What are "public statement" hearings?
Q. What is a "limited appearance"?
Q. What are "trial-type evidentiary" hearings?
Q. What is "discovery"?
Q. If the Siting Board does not personally conduct the hearings, how does it become informed of the proceedings?
SITING BOARD DECISIONS - TIMING OF THE DECISION
Q. Is there a deadline by which the Siting Board must make a final decision on an Article 10 application?
Q. What happens to the deadline if the application is amended during the Article 10 proceeding?
Q. Are there any other exceptions to the deadlines described above?
A. Yes, but only in an unusual circumstance. If the proceeding is on certain qualifying applications by an owner of an existing major electric generating facility to modify that facility or site a new major electric generating facility adjacent or contiguous to the existing facility, the deadlines are different such that the final decision by the Siting Board must be completed within 6 months, the extension permitted in extraordinary circumstances is 3 months, and the extension permitted to consider a material and substantial amendment to the application is 3 months, unless the deadlines are waived by the applicant.
SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION
Q. What options does the Siting Board have in making a decision on an Article 10 application?
Q. What substantive matters must be addressed in any Siting Board decision to grant an Article 10 certificate?
Q. What are the required statutory findings that must be made by the Siting Board?
Q. What are the required statutory determinations that must be made by the Siting Board?
Q. What are the required statutory factors that must be considered by the Siting Board in making the required determinations?
COMPLIANCE AND ENFORCEMENT
Q. Who is in charge of compliance and enforcement matters regarding a Certificate that has been issued?
A. Following any rehearing and any judicial review of the decision, the Siting Board's jurisdiction over an application shall cease, provided, however, that the permanent board shall retain jurisdiction with respect to the amendment, suspension or revocation of a certificate. The Department of Public Service or the Public Service Commission shall monitor, enforce and administer compliance with any terms and conditions set forth in the Siting Board's order granting a certificate.