BASIC CONCEPTS
Q. What is Article 10?
A. "Article 10" was enacted in 2011 to be a portion of the New York State Public Service Law. It is a general state law that is applicable in all of New York State. Article 10 empowers the New York State Board on Electric Generation Siting and the Environment (Siting Board) to issue Certificates of Environmental Compatibility and Public Need (certificate) authorizing the construction and operation of major electric generating facilities.
Q. What is meant by the term "siting"?
Q. What is meant by the term "major"?
Q. What is meant by the term "electric generating"?
Q. What is meant by the term "facility"?
Q. What is meant by the term "certificate"?
THE SITING BOARD
Q. What is the "Siting Board"?
Q. Who are the permanent members of the Siting Board?
Q. What is meant by the term "ad hoc"?
Q. Do ad hoc public members receive any compensation for their service on the Siting Board?
Q. What are the qualifications to be an ad hoc public member?
Q. How are the two ad hoc public members designated to serve on the Siting Board?
A. One is appointed by the President Pro Tem (Majority Leader) of the New York State Senate and one is appointed by the Speaker of the New York State Assembly from a list of candidates submitted to them. The list of candidates is to be submitted
within fifteen days of receipt of notification of the pre-application preliminary scoping statement.
In the event that the President Pro Tem of the Senate or the Speaker of the Assembly does not appoint one of the candidates within thirty days of receiving the list, the Governor shall appoint the ad hoc member(s) from the list of candidates. In the event that one or both of the ad hoc public members have not been appointed within forty-five days, a majority of persons named to the Siting Board shall constitute a quorum.
Q. How is the list of ad hoc public member candidates established?
Q. How is the list of candidates established in the City of New York?
Q. How is the list of candidates established in a town outside of any villages or in a city other than the City of New York?
Q. How is the list of candidates established in a village?
Q. How is the list of candidates established if the facility is to be built on parcels of land located in more than one municipality?
Q. What resources are available to assist the Siting Board?
A. The Department of Public Service provides a presiding examiner and whatever legal, technological, scientific, engineering and other services that may be required. The Department of Environmental Conservation provides an associate examiner. The Secretary and the General Counsel to the Public Service Commission serve as Secretary and the General Counsel to the Siting Board.
TYPES OF GENERATING FACILITIES
Q. What types of electric generating facilities are likely to be proposed pursuant to the Article 10 process?
Q. Are electric generating facilities to be built by a power authority exempt from the Article 10 process?
Q. Are any electric generating facilities exempt from the Article 10 process?
Q. If a facility is exempt from the Article 10 process, can the developer of the facility opt-in to the Article 10 process?
PRE-APPLICATION PROCEDURES - PUBLIC INVOLVEMENT
Q. What is meant by the term "public involvement"?
Q. In what stages of the Article 10 process is it appropriate to conduct public involvement activities?
A. Public involvement is intended to be a proactive process that begins during the planning of a preliminary scoping statement before it is filed, and continues throughout the planning, pre-application, certification, compliance, construction, and operation processes.
Q. How is public involvement conducted?
A. At the earliest stage of the Article 10 process, applicants are required to prepare and begin implementing a Public Involvement Program. In addition, to ensure that the public and interested parties are fully assisted and advised in participating in the Article 10 process,
an Office of Public Information Coordinator has been created within the New York State Department of Public Service.
Q. Is the public required to participate in the applicant's public involvement activities?
Q. What are the purposes of a Public Involvement Program?
Q. What are the elements of a Public Involvement Program plan?
Q. When does the Public Involvement Program plan have to be prepared?
Q. What happens if the Department of Public Service (DPS) finds the Public Involvement Program plan to be inadequate?
A. DPS has 30 days after the date of the applicant's submittal to make written comments on the adequacy of the Public Involvement Program plan. If deemed inadequate, DPS will make specific written recommendations as to what measures are necessary to make the Public Involvement Program plan adequate. Thereafter, the applicant has 30 days to consider the measures recommended by DPS and, in a final written Public Involvement Program plan filed with the Secretary, shall as to each specific measure either revise the Public Involvement Program plan to incorporate the DPS recommendation, or provide a written explanation as to why the applicant is not incorporating the DPS recommendation.
What happens if the applicant refuses to incorporate a DPS recommendation without an adequate explanation, or has an inadequate Public Involvement Program plan?
Q. How do people who do not speak English participate in public involvement?
Q. What is the function of the Office of Public Information Coordinator created within the Department of Public Service?
Q. What is the Department of Public Service?
Q. How can I contact the Office of Public Information Coordinator?
PRE-APPLICATION PROCEDURES - PRELIMINARY SCOPING STATEMENT
Q. What is a Preliminary Scoping Statement?
A. A preliminary scoping statement is a written document to inform the Siting Board, other public agencies and the public that the applicant is contemplating making an Article 10 application. It is prepared by an applicant after consulting with the public, affected agencies, and other stakeholders. The term "consulting" in this context means providing information to and effective opportunities for input from the public, affected agencies, and other stakeholders, concerning the proposal.
Q. When does the Preliminary Scoping Statement have to be filed?
Q. What kind of information must be included in a Preliminary Scoping Statement?
Q. What happens after the Preliminary Scoping Statement is filed?
A. Within 21 days after the filing of the preliminary scoping statement, any person, agency or municipality may submit comments on the preliminary scoping statement by serving such comments on the applicant and filing a copy with the secretary. Within 21 days after the closing of the comment period, the applicant shall prepare a summary of the material comments and its reply thereto, and file and serve its summary of comments and its reply in the same manner as it files and serves the preliminary scoping statement. Thereafter, it is expected that the applicant will work with interested parties to resolve any disagreements they may have about the sufficiency of the planned scope and methodology of studies to be included in the application.
PRE-APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the fund for municipal and local parties?
Q: How does an applicant set up the fund?
A. Applicants supplying the requisite fee to set up the intervenor funding account for the preliminary scoping phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Preliminary Scoping Statement. The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.
Q. What is an "intervenor"?
Q. What is the amount of the intervenor fee assessed during the pre-application stage?
A. Applicants submitting a preliminary scoping statement are assessed an intervenor fee equal to $350 for each 1,000 kilowatts (1 megawatt) of generating capacity of the subject facility, but no more than $200,000. For example, for a 100 megawatt facility, the pre-application intervenor fee would be $35,000 (100 x $350).
Q. What happens if after the pre-application intervenor fees have been used up, the applicant amends its preliminary scoping statement and more review is required?
Q. How does a qualified intervenor make a request for intervenor funds?
Q. When are pre-application intervenor funds awarded?
A. The presiding examiner will provide for an expedited pre-application funding disbursement schedule to assure early and meaningful public involvement. Following receipt of initial requests for pre-application funds, the presiding examiner shall expeditiously make an initial award of pre-application funds. Subject to the availability of funds, the presiding examiner may fix additional dates for submission of fund requests. Thereafter the presiding examiner may make additional awards of pre-application funds, in relation to the potential for such awards to make an effective contribution to review of the preliminary scoping statement.
Q. Who is eligible for intervenor funds?
Q. What can pre-application intervenor funds be used for?
Q. On what basis will the funds be awarded?
A. The presiding examiner will award funds on an equitable basis to participants during the pre-application phase to be used to make an effective contribution to review of the preliminary scoping statement, and thereby provide early and effective public involvement.
PRE-APPLICATION PROCEDURES - STIPULATIONS
Q. What are stipulations?
Q. How is the stipulations process initiated?
Q. Do other parties and the public get an opportunity to participate in the stipulations process?
Q. What happens if a party does not agree that a stipulation entered into between the applicant and another party is adequate?
APPLICATION PROCEDURES - SUBMISSION OF AN APPLICATION
Q. What happens when an Article 10 application is submitted?
A. Within sixty days of receipt, the Chairperson of the Siting Board determines whether the documents submitted comply with the requirements of the law, regulations and stipulations. The Department of Environmental Conservation also advises the Siting Board within the sixty day period whether the documents submitted contain sufficient information.
Q. What happens if the documents submitted are insufficient to comply with the requirements of the law, regulations and stipulations?
A. If the documents submitted are insufficient to comply with the requirements of the law, regulations and stipulations, the Chairperson of the Siting Board will issue a letter to the applicant advising of the deficiencies that must be corrected before the documents can be deemed a complying application.
The Chairperson of the Siting Board may also require the filing of any additional information needed to supplement an application before or during the hearings.
Q. What happens if the documents submitted are sufficient to comply with the requirements of the law, regulations and stipulations?
A. If the documents submitted are sufficient to comply with the requirements of the law, regulations and stipulations, the Chairperson of the Siting Board will issue a letter to the applicant advising that the documents submitted constitute a complying application. The Chairperson will also fix the date for the commencement of a public hearing and the Department of Environmental Conservation will initiate its review pursuant to federally delegated or approved environmental permitting authority or air and water permit applications. Within a reasonable time, the presiding examiner will hold a prehearing conference to expedite the orderly conduct and completion of the hearing, to specify the issues, to obtain stipulations as to matters not disputed, and to deal with other matters deemed appropriate. The presiding examiner will then issue an order identifying the issues to be addressed by the parties. Later in the proceeding there may also be a consideration of additional issues which warrant consideration in order to develop an adequate record.
APPLICATION PROCEDURES - DESIGNATION OF PARTIES
Q. Who are the parties to an Article 10 proceeding?
A. There are three kinds of parties: (a) automatic statutory parties; (b) parties that have a right to be a party merely by giving notice; and (c) parties that may be permitted to join.
Q. Who are the automatic statutory parties to an Article 10 proceeding?
Q. Who are the parties that have a right to be a party to an Article 10 proceeding merely by giving notice?
A. Provided they file with the Siting Board a notice of intent to be a party, within 45 days after the date given in the published notice as the date for the filing of the application, the following parties have a right to be a party to an Article 10 proceeding merely by giving the required notice: (a) the affected municipality; (b) any individual resident of an affected municipality; (c) any non-profit corporation or association, formed in whole or in part to promote conservation or natural beauty, to protect the environment, personal health or other biological values, to preserve historical sites, to promote consumer interests, to represent commercial and industrial groups or to promote the orderly development of any area in which the facility is to be located; and (d) any other municipality or resident of such municipality located within a five mile radius of such proposed facility
(their notice of intent must include an explanation of the potential environmental effects on such municipality or person). In addition, the presiding officer may for good cause shown permit a municipality or other person to become a party and to participate in all subsequent stages of the proceeding.
Q. Who are the parties that may be permitted to join?
Q. Where does a party file a notice of intent to be a party?
APPLICATION PROCEDURES - Fund for Municipal & LOCAL PARTIES
Q. What is the amount of the intervenor fee assessed when an application is filed?
Q. How does an applicant set up the fund?
A. Applicants supplying the requisite fee to set up the intervenor funding account for the application phase of the case must provide a check, made out to the NYS Department of Public Service, simultaneously with the filing of their Application.
The case number must be printed on the face of the check. The check must be delivered to the Director of the DPS Office of Finance and Budget, under cover of a letter stating the amount of the check and the Article 10 case name and number. The letter must be copied to the Secretary of the Siting Board for filing in the Article 10 case.
Q. What happens if after the application phase intervenor fees have been used up, the applicant amends its application and more review is required?
Q. How does a qualified intervenor make a request for intervenor funds?
Q. Who is eligible for intervenor funds?
A. All municipal and local parties to the proceeding are eligible for application phase intervenor funds. The presiding examiner shall reserve at least 50% of the application phase funds for potential awards to municipalities.
Q. What can application phase intervenor funds be used for?
A. The intervenor funds awarded can be used
to defray expenses incurred by municipal and local parties for expert witnesses, consultants, administrative costs (document preparation and duplications costs) and legal fees. No intervenor funds may be used to pay for judicial review or litigation costs.
Q. On what basis will the funds be awarded?
HEARING PROCEDURES - CONDUCT OF THE HEARING
Q. Who conducts the hearings?
Q. What kinds of hearings will be held?
Q. What are "public statement" hearings?
A. Public statement hearings are designed to obtain input from the general public. The format is designed for the taking of unsworn oral statements, although written statements ordinarily may also be submitted. Parties to the proceeding are not permitted to cross examine the persons making such statements.
Q. What is a "limited appearance"?
Q. What are "trial-type evidentiary" hearings?
Q. What is "discovery"?
Q. If the Siting Board does not personally conduct the hearings, how does it become informed of the proceedings?
A. A written transcript record is made of the hearings and of all testimony taken and the cross-examinations thereon. In addition, the presiding examiner will provide a summary of the proceedings in a recommended decision that will be presented to the Siting Board. The parties will also present legal briefs to the Siting Board with citations to the portions of the record they deem relevant to their positions.
SITING BOARD DECISIONS - TIMING OF THE DECISION
Q. Is there a deadline by which the Siting Board must make a final decision on an Article 10 application?
Q. What happens to the deadline if the application is amended during the Article 10 proceeding?
A. If during the proceeding there is a material and substantial amendment to the application, the deadlines may be extended by no more than 6 months to consider such amendment, unless the deadline is waived by the applicant.
Q. Are there any other exceptions to the deadlines described above?
SITING BOARD DECISIONS - SUBSTANCE OF THE DECISION
Q. What options does the Siting Board have in making a decision on an Article 10 application?
Q. What substantive matters must be addressed in any Siting Board decision to grant an Article 10 certificate?
A. The Siting Board is required to make certain statutory findings and determinations, and the required determinations can only be made after considering certain required factors.
Q. What are the required statutory findings that must be made by the Siting Board?
Q. What are the required statutory determinations that must be made by the Siting Board?
Q. What are the required statutory factors that must be considered by the Siting Board in making the required determinations?
COMPLIANCE AND ENFORCEMENT
Q. Who is in charge of compliance and enforcement matters regarding a Certificate that has been issued?